Despegue ← Projects Proyecto RIGI
The 31 projectsPROJECT ▾
Neuquén
YPF 'LLL Oil' (shale-oil mega-development)Pluspetrol - Bajo del Choique / La InvernadaTecpetrol - Los Toldos II EstePampa Energía - Rincón de ArandaTGS - Natural gas liquids (NGL) project, Tratayén - Bahía BlancaAmpliación Mega - natural gas liquids (NGL)
San Juan
Vicuña (Josemaría + Filo del Sol) — copper, gold and silverEl Pachón - copper, silver and molybdenum (Glencore)Los Azules — copper cathodes (McEwen Copper)Gualcamayo — Deep Carbonates (DCP): gold and silver (Minas Argentinas)Leaching Phases 8 and 9 expansion — Veladero Mine (gold)
Catamarca
Agua Rica / MARA — copper, gold, silver and molybdenum (Glencore)Salar Tres Quebradas (3Q), stage 2 — lithium carbonate (LIEX/Zijin)Fénix — Phase 1B Expansion: lithium carbonate (Minera del Altiplano / Rio Tinto)Hombre Muerto Oeste (HMW) — lithium carbonate (Galan)
Río Negro
Argentina LNG (YPF, Eni and XRG)Southern Energy - floating LNG (Argentina LNG, Hilli phase)Vaca Muerta Oleoducto Sur (VMOS)San Matías Gas Pipeline (San Matías Pipeline S.A.) - evacuation of Vaca Muerta gas to the Atlantic
Salta
Pozuelos-Pastos Grandes (PPG)Rincón Project — lithium carbonate (Rio Tinto)Diablillos — gold and silver (Salta/Catamarca)Sal de Oro II — lithium carbonate (POSCO)
Buenos Aires
Fértil Pampa — urea and ammonia plant in Bahía BlancaSidersa Argentine Steel Project — long steel productsOlavarría Wind Farm (P.E. Olavarría) — wind generation (GEAR I / PCR + ArcelorMittal Acindar)
Mendoza
PSJ Cobre Mendocino (San Jorge) — copper and goldEl Quemado Solar Park and Annexes — photovoltaic generation (Luz del Campo SA / YPF Luz)
Jujuy
Cauchari-Olaroz Expansion — lithium carbonate (Exar)
La Pampa
Perito Moreno Gas Pipeline expansion (ex-GPNK) - TGS
Santa Fe
Timbúes Multipurpose Terminal — port infrastructure (Terminal Timbúes SA)
ESEN
up to date · reviewed Oct 7, 2026
Mining - Lithium/Catamarca
approved

Hombre Muerto Oeste (HMW) — lithium carbonate (Galan)

regime-eligible assets
217,09USD M
operator
GALAN LITIO SA
approving act
Resolución 1271/2025
what it will need
3procurement fronts

Lithium brine project in the Salar del Hombre Muerto (western zone), to produce 12,000 t/yr of lithium carbonate equivalent. Official portal: 670 jobs (direct and indirect).

Summary
share among the 24 approved RIGI projectstotal USD 42,134 M
Hombre Muerto Oeste0.5%
the other 23USD 41,917 M
what stage it is atfirst production verif Jun 30, 2026 ↗

How to supply it

what we have for a supplier, and how to request it

What we have on this project for a supplier

How to get in
1 registration route, with its status · 6 requirements with the rule that sets each one · 6 steps in order, with their timing

Who decides the purchase, who you invoice and where a new supplier registers.

What it buys and when
1 phase, with what it buys · 1 happening now

Which lines each phase buys and when the window opens for each one.

What it is missing
3 services it will need and has no supplier for yet

Which they are, why it will need them and who could provide them.

Who is already in
1 company with a contract on the works

Who they are, what each one does and how to sell to them.

All of this is surveyed and verified against its source. Crossed with what you sell —which of them your products suit, how to reach it and when— it is in your company report. Request the report

Does your company fit into Hombre Muerto Oeste?

We cross what your company does against the projects we track and tell you which ones it fits into, through which door and who it competes against. Two pages, with the evidence behind them.

Where my company can get in

The project

what it is, the route, the owners, the works and the contractors

Who owns it

GALAN LITIO SA (CUIT 30-71736364-3); RIGI vehicle: its Dedicated Branch (CUIT 30-71899846-4). Parent: Galan Lithium Ltd (ASX: GLN). verif Aug 28, 2025 ↗

The works, milestone by milestone

Oct 1, 2026announced inauguration

The Government of Catamarca announces that Galan will inaugurate its Hombre Muerto Oeste plant in October 2026, with no confirmed date, with a projected 5,000 t per year.

Sep 30, 2026provincial agreement

Galan Litio and the Government of Catamarca sign two agreements: an addendum to the Acta Compromiso adapting it to the RIGI framework, with a contribution of 50% of the estimated royalty from the first year of sales for works in Antofagasta de la Sierra, and a one-off contribution of USD 300,000 to the mining royalties trust fund for the upgrade and new routing of Provincial Route 43.

Jul 31, 2026expansion works

Galan states that the pond works for the Phase 1 expansion —from 4,000 to 5,200 t/yr of lithium carbonate equivalent— start within the September 2026 quarter, with the capacity uplift targeted at the first half of 2027 and no plant modifications. Verbatim: «pond construction works will commence within the September 2026 quarter».

Jun 30, 2026first production

Verbatim from the issuer: «The June 2026 quarter marked Galan's transition from developer to producer», with the plant's wet commissioning completed and the first production of processed lithium chloride.

Feb 19, 2026contribution to route 43

Galan Litio and the Government of Catamarca sign the agreement for a voluntary and exceptional contribution of USD 250,000 to the mining royalties trust, for the first 60.3 km stretch of Ruta Provincial 43 between Antofagasta de la Sierra and the Salta border.

Aug 28, 2025Boletín Oficial

Resolución 1271/2025 of the Ministry of Economy is published, approving the adhesion: USD 217,090,266 computable, 12,000 t/yr of lithium carbonate equivalent, and the highest local-content commitment in the published portfolio, 95.34% of the amount earmarked for paying suppliers.

Jul 17, 2025RIGI adhesion

The project's RIGI adhesion date, fixed by the act that later approved it.

What it leaves in Catamarca

jobs, works, taxes, promises and the outlook

The place where it is built

Antofagasta de la Sierra, Catamarca, before the RIGI: the official snapshot of November 2023, counting the people who live there.

Registered jobs held by people who live there

1,524 jobs in November 2023, 52% of them in public administration verif Nov 2023 ↗

Miners and construction workers who live there

211 jobs: 124 in mining and 87 in construction verif Nov 2023 ↗

Miners who live there, 2018 versus 2023

from 50 to 124 jobs verif Nov 2023 ↗

Lodging businesses with employees in the department

0 in 2022 verif 2022 ↗

Mining wage versus public-sector wage

2.2 times estim Nov 2023

The works that stay behind

The infrastructure that stays standing once the works end, with its size and its source.

First paved stretch of Ruta Provincial 43, between Antofagasta de la Sierra and the Salta border

Roads
60.3 km

of base works and paving, with a USD 250,000 contribution from Galan Litio to the trust that finances it

The towns of the Catamarca Puna and anyone who uses the road. The work belongs to the Dirección Provincial de Vialidad and remains a provincial route: it is not a private mine road, and the miner's contribution is applied to paying progress certificates on a public work.

The contribution is channelled through the Fondo Fiduciario de Regalías Mineras, on the basis of article 3.1 of the mining trust agreement, and is paid in a single disbursement within five business days of signing. The Dirección Provincial de Vialidad is the contracting authority.

Pending · 2 blocks
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall it

risks and how to track them
Pending · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified this

the act, the gaps and the sources

The RIGI act, in detail

Administrative file number

EX-2024-118669988- -APN-SCEYM#MEC verif Aug 28, 2025 ↗

Accession date

Jul 17, 2025 verif Aug 28, 2025 ↗

The act’s articles, in detail

4 facts on the commitment
Local content set by the act

95,34 % of the amount earmarked for suppliers that goes to LOCAL suppliers verif Aug 28, 2025 ↗

What that local content is calculated on

The entire investment amount earmarked for paying suppliers, goods and infrastructure works, during the construction and operation stages verif Aug 28, 2025 ↗

Deadline for the commitment

31 December 2029 to complete the minimum investment amount. verif Dec 31, 2029 ↗

Vehículo de Proyecto Único

GALÁN SDE (dedicated or special branch of Galán Litio S.A.), tax ID 30-71899846-4, registered at Rivadavia 378, city of Salta. verif Aug 28, 2025 ↗

What we could not confirm

There are 2 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01How many people the construction employs and how many stay working in operation+

No RIGI admission resolution publishes the figure: the seventeen that are published state that the company «provided the estimate of direct and indirect employment of the Project with local integration» and do not transcribe it. The official RIGI portal publishes a single figure that adds direct and indirect jobs together and does not separate the two stages, and mixing them is exactly the error the `empleo` field exists to prevent.

What would close itThe employment study filed with the application, or a company release splitting the figure into construction and operation.
H-02Who is building the ponds and the civil works of Hombre Muerto West+

Neither the issuer's quarterly report nor the feasibility study publishes the name of the ponds, earthworks or camp contractor. The feasibility study goes as far as saying that the preferred ponds contractor must install a workshop on site, and still does not name it. Two independent investigations of this project declared the gap separately, which is the sign that the absence belongs to the world and not to the search.

What would close itAn award announcement from Galan, or the contractor's own project sheet, which is how the contractors of the other three Catamarca projects in this batch surfaced.
First step · free
The first read of your company

We look at what your company does and tell you whether we see a sign that it fits this market, with the evidence behind it. If we do not see one, we say so too and name the condition that would change it. One page as a dated PDF, within 48 working hours.

Not here for a company? Invest · Work (in Spanish) · Start a business (in Spanish) · Institutions
Page 1 of the example executive summaryOpen the report ↗A real analysis · a real company, open in full →
Ignacio Aredez
Analysis and curation: Ignacio Aredez
Head of Despegue
Method and track record →
  • 20+ years in technology, 15 of them in data and AI, for clients across Europe and the Americas
  • Certified in AI governance (ISO/IEC 42001)
  • Machine Learning (Google Cloud)
  • Registered expert with the European Commission
How to read the seals →
  verif primary source · prob primary source pending · unconf a source said it · estim our own calculation · thesis our reading · the date belongs to the datum, at the precision its source allows
This is not financial advice. The page is built on the act that approved the project and the source of every figure, with the gaps declared. What the company announces is published as an announcement, and what is our own reading is labeled as thesis. ← Back to Catamarca