Despegue Río Negro Proyecto RIGI ESEN
up to date · reviewed Aug 20, 2026
Energy - Oil and Gas/Río Negro
approved

Vaca Muerta Oleoducto Sur (VMOS)

regime-eligible assets
2.486USD M

437 km, 30-inch export pipeline between Allen and Punta Colorada, with a marine terminal of six tanks and two monobuoys six kilometres offshore, in the San Matias Gulf. It takes Vaca Muerta crude out through the Atlantic, without going through Buenos Aires or Chile. The resolution that approved it under RIGI recognises a base capacity of 377,400 barrels per day; the consortium tells the market it starts at around 180,000 and reaches 550,000 in the second half of 2027. Works were 80% complete in July 2026 and the first export is expected in early 2027.

Capacidad base del acto
377,400 barrels per day
Al arranque
Around 180,000 barrels per day when the first crude comes out
En régimen
Around 550,000 barrels per day in the second half of 2027, with a maximum design of 700,000
first production
early 2027
Summary
share among the 22 approved RIGI projects we tracktotal USD 33,041 M
Vaca Muerta Oleoducto Sur7.5%
the other 21USD 30,555 M
what stage it is atunder construction· primera producción early 2027 verif · Jul 2026

The projectwhat it is, the route, the owners, the works and the contractors

What it is and why it exists

A 437-kilometre pipeline carrying Vaca Muerta crude from Allen to the sea at Punta Colorada, and a terminal where vessels load six kilometres offshore. It was built by the nine oil companies that will then use it: they put up the money, signed the transport commitment and created a company, VMOS S.A., which owns the pipeline and does not produce oil.

Vaca Muerta produces more crude than it can move out. The existing pipelines run to Bahía Blanca and to Chile, and they hit their ceiling. Without a new outlet to the Atlantic, production stalls even with wells drilled: the surplus cannot be sold. That is why the producers themselves are paying for the pipeline, and why they committed 490,000 barrels a day firm before the pipe existed — they pay for the capacity whether they use it or not, and that commitment is what allowed VMOS to secure a USD 2,000 million loan.

Where it runs and how much it can move

Route

437 kilometres between Allen and Punta Colorada, both ends within Río Negro. Vaca Muerta crude reaches Allen through other pipelines that are not part of this project verif · Mar 21, 2025

Diameter

30 inches verif · May 26, 2025

Terminal

Punta Colorada, in the municipality of Sierra Grande, on the San Matías Gulf. Vessels are loaded at two single-point buoys six kilometres offshore, not at a pier verif · Mar 21, 2025

Length according to the province

441 kilometres. It is nobody's mistake: it is the figure Río Negro uses to assess the environmental levy, while the descriptive memorandum of that same agreement says 437. Both figures coexist inside the same instrument verif · May 26, 2025

Storage

3,774,000 barrels according to the national resolution, expandable to 6,290,000. The agreement with the province describes the tank farm as built: six tanks of 120,000 m³ at Punta Colorada and three of 50,000 m³ at Allen verif · May 26, 2025

Ship loading

Potential of 700,000 barrels per day across the two single-point moorings verif · Mar 21, 2025

Power

The pumping stations plug into the Comahue public grid, not into their own generation. The national regulator published two new demands: 11.34 MVA for the Allen head station and 8.10 MVA for the Chelforó pumping station, with two new 132/6.6 kV transformer stations — 24 MVA at Allen and 10 MVA at Chelforó — and just 600 metres of high-voltage line to connect them. They are operated by Transcomahue, the provincial transmission company prob · Jul 22, 2025

Construction water at the terminal

Groundwater from two private wells, Olivar 2 and Olivar 6, with a maximum authorised flow of 25 m³ per hour between them. The permit covers only «construction and commissioning», lapses if the use changes and expires after four years verif · Jun 11, 2025

Water at the Allen head station

Surface water from the Alto Valle Main Irrigation Canal, 42.5 m³ per hour, for the fire-fighting network and industrial uses during construction. It carries a seasonal restriction written into the permit itself: during the shutdown period the canal runs dry verif · Sep 19, 2025

Pumping

Four pumping stations and 28 block valves along the 437 kilometres prob · 2026

What reserves back it

Commercial backing

490,000 barrels a day committed firm by the shareholders before the pipeline existed. YPF put in 120,000, Vista 50,000 and Pampa 50,000; the remaining 270,000 are split among six shareholders that are not listed and do not publish their volume. That commitment is the security for the USD 2,000 million loan verif · Dec 31, 2025

The reserves that fill it

The pipeline has no reserves of its own: it transports those of its shippers. The Neuquén unconventional basin held 1,546 million barrels of proved oil reserves as of 31 December 2023, the most recent official published record. The largest blocks behind that figure are La Amarga Chica with 250, Loma Campana-LLL with 247, Bajada del Palo Oeste with 173 and Bandurria Sur with 143 million barrels prob · Dec 31, 2023

Who owns it

The company

VMOS S.A., CUIT 30-71871335-4. It is a company created for this work by the same oil companies that will use the pipeline. verif · Dec 31, 2025

The shareholder register

Nine groups, eleven entities: Chevron and Shell each come in through two companies. Gas y Petróleo del Neuquén is the only Class B shareholder; the rest are Class A. verif · Dec 31, 2025

YPF

24.49% as of 31 December 2025. The shareholders' meeting of 23 April 2026 approved expanding its capacity, which would take it to 29.82%, but YPF itself states that the subscription is still pending payment verif · Dec 31, 2025

Vista Energy

10,20% verif · Dec 31, 2025

Pampa Energía

10.20% at the close of 2025 and 9.09% as of 30 June 2026, because the base it is calculated on grew verif · Jun 30, 2026

The other six

Pan American Sur, Pluspetrol, Chevron, Shell, Tecpetrol and Gas y Petróleo del Neuquén are not listed and do not publish their stakes. Tecpetrol came in in June 2025, after the rest verif · Dec 31, 2025

Who runs it

No shareholder controls the company, but YPF runs it: Gustavo María Gallino, YPF's Vice President of Infrastructure, is a director and chairman of the board of VMOS. The CEO is Gustavo Chaab prob · Dec 31, 2025

Equity

USD 301 million at the close of 2025, with a net loss of USD 51.4 million for the year. As of 30 June 2026 equity was up and the half-year result had turned positive, still without transporting a single barrel verif · Dec 31, 2025

What other projects it links to

What this project enables or needs outside the province, and through what mechanism.

NeuquénThe project ends in Río Negro but its reason for existing is in Neuquén: it carries crude from Vaca Muerta verif · Aug 10, 2026 +

The effect runs both ways — without this outlet to the Atlantic, Neuquén's production stalls even with wells drilled, and without that production the pipe does not fill.

YPF filed its LLL Oil project under the RIGI in May 2026, with an investment estimated at USD 25,000 million over fifteen years and more than 1,150 wells, and states that it is exported entirely through VMOS verif · Aug 10, 2026
NeuquénAnother RIGI project shares this pipeline's right-of-way and is assessing reusing its construction camps: the San Matías Dedicated Pipeline, of San Matías Pipeline S.A., which supplies the floating LNG project in the Golfo San Matías verif · Feb 2026 +
The Environmental Impact Study of the San Matías Dedicated Pipeline states that «se compartirá la traza con el Oleoducto VMOC-VMOS que se encuentra siendo construido por YPF» and that «se evaluará la posibilidad de reutilizar los sitios empleados por los obradores de dicho proyecto», to be defined in the Detailed Engineering verif · Feb 2026

The works, milestone by milestone

Jul 2026progress

The works reach 80% and the operator confirms to the market that the first export sails in early 2027

Jun 16, 2026offshore works

The anchors and chains that will hold the two single-point moorings are set on the floor of the Golfo San Matías

Mar 20, 2026river crossing

The pipeline crosses the Río Negro beneath the riverbed, 25 metres deep, in the Chelforó area. It had been scheduled for December 2025: it is the only schedule slippage documented with an official source on both sides

Nov 1, 2025welding

Final automatic weld of the pipeline at the entrance to the Punta Colorada terminal. In October the Techint-SACDE joint venture had set a record of 175 joints and more than four kilometres in a single day

Jul 8, 2025financing

VMOS signs an international syndicated loan of USD 2,000 million over five years, secured by the transport contracts and by the partners' Class A shares

May 26, 2025provincial agreement

The Río Negro legislature ratifies through Ley 5782 the agreement with VMOS: a one-off bond of USD 60 million and a community contribution of USD 40 million a year for thirteen years

Mar 21, 2025official gazette

Resolución 302/2025 is published, approving accession to the RIGI as a Long-Term Strategic Export Project

Mar 6, 2025rigi accession

RIGI accession date set by article 2 of the resolution. The thirty years of stability hang from this date

Dec 13, 2024decision to build

The board of VMOS S.A. unanimously approved the construction of the pipeline. The same day the four founding partners signed the shareholders' agreement and the first firm transport contracts

Who already has a contract

UTE Techint - SACDEDomestic
EPC of the trunk pipeline: 437 km of 30-inch pipe in two sections, around 110 km from Allen to Chelforó and 327 km to Punta Colorada, with more than 35,000 welds and 72,000 hours of detail engineering

EPC contract with VMOS S.A., works started in February 2025

Milicic y CB&IDomestic / international
Punta Colorada terminal and six-tank farm

Terminal works, including the early water supply and power feed works

DOF Group ASANorway
Installation of the mooring system for the two SPM buoys, pipeline end manifold, tie-in spools, hook-up and diving, with the vessels Skandi Hera and Skandi Patagonia

A contract of more than 250 days of work at sea, across two campaigns during 2026, worth what the company itself classifies as between USD 25 and 50 million

Tenaris / SIATDomestic
Supply of the steel pipe, with concrete coating for the subsea section

More than 10,100 tonnes of pipe shipped from Dock Sud for the marine front

AESADomestic
Allen and Chelforó pumping stations

Electromechanical works of the pumping stations

EcosanDomestic
Construction of the work camps

More than 1,000 modules across two camps

Compañía Rionegrina de Alimentos S.A.S.Río Negro
Catering and packed meals for the Punta Colorada Terminal camp, in a joint venture with South Management

It is the only Río Negro company with a VMOS contract confirmed by name. The service covers around 1,500 workers

How to supply itwhere to register, what they ask for and what they will buy

How to become a supplier

Who you invoice

VMOS S.A., CUIT 30-71871335-4, registered office at Ingeniero Enrique Butty 235, Ground Floor, Office 1, CABA, and special domicile in the province at 25 de Mayo 196, Viedma. Watch out for which company: the operation under the regime runs through RIGI - VMOS S.A., CUIT 30-71890264-5, a separate tax identification created by order of article 10 of the resolution. The province removed VMOS S.A. as a withholding agent for that reason. And in practice most local suppliers invoice neither of the two: they invoice the contractor.

Who decides the purchase

The procurement area of VMOS S.A., a company with no controlling shareholder: YPF is the largest with less than a third and runs it in practice —its Vice President of Infrastructure chairs the board— but no decision goes through without a coalition. The local door is one step below: the large packages go to four contractors —the Techint-SACDE joint venture on the pipeline, Milicic on the terminal, AESA and OPS on the pump stations— and they are the ones who build their own supply chain.

The registration routes that exist today, with their status. The one that is up and running is not always the official one.

Río Negro Suppliers Register (Ley 5805)

up and running today

This is the provincial single window and it is populated today: when the regulation was issued it held 476 companies, of which 308 registered, 129 pre-registered, 12 conditional, 15 out of date, 11 pending and one rejected. Certification is valid for a year and is renewable. There is a figure designed for the outsider who wants to set up locally: the Conditional Río Negro Supplier, with a relocation plan of up to 24 months

Go to the single windowabrir

What they ask you for

Local roots

Established in Río Negro: the provincial hydrocarbon transport law requires hiring workers and suppliers established in the province at a share of no less than 80%, and that obligation also reaches contractors and subcontractors, which is where the buying actually happens verif · Sep 29, 2022 Ley provincial 5.594, article 8: «Los sujetos alcanzados por la presente, así como sus contratistas y subcontratistas, deberán contratar trabajadores y proveedores radicados en la jurisdicción de la Provincia de Río Negro en un porcentaje no inferior al ochenta por ciento (80%), salvo causa debidamente acreditada ante la autoridad de aplicación, para todas aquellas tareas que deban ejecutarse en territorio provincial»

Legal

Being registered in the Río Negro Suppliers Register so that the purchase counts as local content and so that the company is required to invite you to bid prob · Jul 1, 2026 The regulation of Ley 5805 sets a floor of 60% of contracting with Río Negro suppliers and mandatory invitation of the companies listed in the register

Certification

The RIGI ad hoc certificate of national origin, if what you sell is goods and you want them to count towards the project's supplier plan prob · Feb 25, 2025 It is created by Resolución 19/2025 of the Secretaría de Industria y Comercio, issued by authorised bodies, does not require proving prior exports and is valid for two years. Its number must appear on the commercial documents

The order you get in by

1

Aim at the phase you want to sell to, not at the project. The pipeline is already welded and the tanks are being assembled: the civil works and right-of-way welding packages have already been awarded. What is being bought today is the offshore front, and what has not been bought yet is the operation now

2

Register in the Río Negro Suppliers Register. Outside the register they are not required to invite you to quote, and your sale does not count as local content in any report annual certification, renewable

3

Target the contractor, not the owner. The big four —Techint-SACDE, Milicic, AESA and OPS— build their own chain, and that is where a Río Negro SME gets in depending on the work front

4

If you are from outside the province, the route is the Conditional Río Negro Supplier with a relocation plan: the law asks for local roots, not a borrowed office up to 24 months

What it will buy, and when

Each phase buys different things at different times. The links lead to the matching market or trade.

happening now2 phases

Pump stations and tanks

en curso
2026

Four pump stations, the Allen head station with three tanks and the six-tank farm at Punta Colorada, with their geodesic domes and hydrostatic testing. Each tank needs fourteen days of controlled filling before it can be used: roofing it does not put it into service.

1 service to contract
2 trades to hire

Subsea pipeline and single-point moorings

en curso
2026

This is the active phase today and the only stretch of the corridor with no installed local capacity: some five kilometres of concrete-coated pipe, two CALM-type single-point moorings six kilometres offshore, 43-tonne anchors and 400-metre chains. The work is done by vessels and contractors from abroad.

1 service to contract
1 trade to hire
not started yet5 phases

They are not buying any of this today. Open the phase to see the detail and arrive qualified the day it goes to tender.

Engineering, permits and procurement2022 a 2025hecha1 ítem+

Environmental impact study, public hearing, EPC award and purchase of pipe, plate and equipment. This is the phase where it is decided who gets to bid: by the time construction starts, the large packages are already closed.

1 service to contract

No trades specific to this phase.

Right-of-way clearing and earthworks2025hecha3 ítems+

More than 300 kilometres of right-of-way opened in the first months, with three camps and 7- and 14-day rotations. It is the phase that moves the most people and the first to reach local suppliers of transport, catering and accommodation.

1 service to contract
2 trades to hire
Pipe laying and welding2025 a 2026hecha2 ítems+

Automatic welding of the 437 kilometres, with 76 special crossings of roads and streams and the crossing of the Río Negro beneath the riverbed. It closed at the terminal entrance in November 2025.

2 trades to hire

No services specific to this phase.

Line fill and first exportlate 2026 to early 2027pendiente1 ítem+

Line fill of the pipeline and the first loaded vessel. The threshold the company's chairman stated is having at least two tanks and one single-point mooring in operation.

1 service to contract

No trades specific to this phase.

Operation and maintenancefrom 2027pendiente4 ítems+

The shift almost nobody is watching: a marine terminal operating 24 hours a day needs maintenance, tugs, diving, pipeline integrity inspection, spill response and environmental monitoring for decades. That market has no owner yet on the Río Negro coast.

2 services to contract
2 trades to hire

No catalogued supplier yet: Spill response and OSRO vessels · Marine environmental monitoring of the Golfo San Matías

Looking for work rather than to supply? What this project leaves the people of Río Negro (in Spanish)

What it will need and has no supplier for yet

tesisOur own reading of the project, not company-reported data.

Operation and maintenance of the marine terminal

high

The terminal runs 24 hours a day for decades and needs electromechanical maintenance, integrity inspection, diving and tugboats. This demand starts when construction ends, not before, and today it has no established supplier on the Río Negro coast.

Supplied byIndustrial / marine services

Spill response and marine environmental monitoring

high

A crude export terminal in a gulf with protected areas requires a contingency plan, response equipment and continuous monitoring. The conditions attached to the environmental permit are, in practice, the specification for this service.

Supplied byEnvironmental services

Personnel transport and camp logistics

high

It is the largest line in purchases from Río Negro suppliers, at ARS 5,164 million in a single quarter, above any technical service. Demand is continuous while construction lasts and shrinks, without disappearing, once in operation.

Supplied byLogistics / transport

Catering, meals and accommodation

high

The second-largest line by amount in the quarter, at ARS 4,059 million, and the only one with a Río Negro company holding a contract confirmed by name. Sierra Grande absorbs 60% of the corridor's demand.

Supplied byCatering / hospitality

Metalworking, boilermaking and electromechanical assembly

high

The tanks, the pumping stations and the substation require certified welding, assembly and non-destructive testing. Provincial law requires 80% of suppliers to be based in Río Negro, and that obligation reaches the contractors, which is where the buying happens.

Supplied byMetalworking

Marine services: towage, diving and offshore support

medium

The two single-point moorings concentrate the loading operation and today the work is done by a foreign fleet hired campaign by campaign. It is the only stretch of the corridor with no installed local capacity, and therefore the clearest market gap.

Supplied byMarine services
Weekly newsletter · free

Get on board the takeoff

This week’s updates: proyectos RIGI, proveedores y datos verificados de Río Negro and new provinces as they launch. Free.

no spam we read every one
Which are you?
What are you looking for?
Tell us more
Your provinces Río Negro empty = all
pick one or more

What it leaves in Río Negrojobs, works, taxes, promises and the outlook

How many jobs it creates

In construction

Around 2,000 people at peak construction, according to the pipeline contractor itself. The official RIGI register assigns the project 3,108 direct and indirect jobs, without distinguishing construction from operation prob · 2026

The works that stay behind

The infrastructure that stays standing once the works end, with its size and its source.

Provincial Route 9, stretch from Route 3 to the Punta Colorada pier

vial
28 km

of gravel road between Route 3 and the pier

Sierra Grande and Punta Colorada

Funded by the VMOS Bond. It is gravel, not asphalt: grading, embankments, culverts, guardrail and signage. Bids were opened in April 2026 with five bidders and by mid-year it was still not awarded

Expansion of School 60 in Sierra Grande

social
640

m² sports hall

Sierra Grande

A multipurpose hall with gym, gender-separate toilets, accessibility, kitchen and lobby with independent entrance, for $1,410,543,073 and a twelve-month term, funded by the VMOS Bond. It stays open to the public for sports and social activities

Refurbishment of the Sierra Grande Hospital, stage 2

social
$324 M

official budget

Sierra Grande

Roofing, ceilings, storm and sewage drainage and vehicle access at the Dr. Osvaldo P. Bianchi Hospital, with the works delegated to the municipality and a term of 150 calendar days from the start certificate. The decree approves and funds the works: as of 30 July 2026 the agreement was still «to be signed» and there was no start certificate

Transfer to the Municipality of Sierra Grande

otra
$3,780 M

transferred to the municipality

Sierra Grande

This is the 5% of the Bond that the law reserves for the municipality, and it is the only completed movement of funds we could document. Stated purpose: road machinery, 1,000 LED streetlights and 14,590 m² of paving. The mayor submits the projects but the province has to approve them before the money is transferred

Hospitals in Sierra Colorada and Barda del Medio

social
USD 17 M

between the two: 10 in Sierra Colorada and 7 in Barda del Medio

Río Negro (not the corridor)

Two new hospitals funded by the VMOS Bond, hundreds of kilometres from the pipe. This is the structural fact worth keeping in view: the works the pipeline leaves behind are provincial, not local. The Bond also pays for schools in El Bolsón, Cipolletti, General Roca, Fernández Oro and Luis Beltrán. Sierra Grande, the municipality that hosts the terminal, gets the 5% plus whatever the province decides to allocate to it

What it already pays in taxes and royalties

Item by item, with the rule that sets it. A rate is not the same as what is collected, nor what is received the same as what is projected.

5/95%Territorial Development Contribution (the «VMOS Bond») verif · May 26, 2025 +
USD 60,000,000, payable within sixty calendar days of the agreement taking effect. The law that creates it locks down what it can be spent on: it funds equipment or works that improve quality of life, competitiveness, safety and sustainability, «con expresa prohibición de aplicar los mismos a gastos corrientes». The province reported having collected it in July 2025 verif · May 26, 2025
Municipality of Sierra Grande5%
Province of Río Negro95%
Base: One-off payment for the project, charged to article 10 of Ley provincial 5.594
Who it goes to: the province
Ley provincial Q 5782, Acta Acuerdo art. five point 5.1
USD 40,000,000Community Contribution verif · May 26, 2025 +
USD 40,000,000 a year for thirteen years, that is USD 520 million in total. The first payment fell due before 27 February 2026 and the following ones fall due before 28 February each year. It goes to investments and works in safety and health «y cualquier otro tipo de inversión que decida realizar la provincia». It is the agreement's only obligation to report what the money was spent on, and it is striking who it is reported to: the Contaduría General reports the allocation of funds to VMOS S.A., not to the Tribunal de Cuentas or the legislature verif · May 26, 2025
Base: Annual, for thirteen years counted from 1 January 2026
Who it goes to: the province
Ley provincial Q 5782, Acta Acuerdo art. five point 5.2
USD 1,050,000Control and Oversight Fee verif · May 26, 2025 +
USD 1,050,000 a year. It funds the province's oversight and policing powers over the pipeline verif · May 26, 2025
Base: Annual and in advance, by 31 January each year
Who it goes to: the province
Ley provincial 5.594 art. 11; Acta Acuerdo art. five point 5.4
Environmental fee verif · May 26, 2025 +
It is assessed on physical parameters that the agreement itself sets: 441 kilometres of length, 87,440 m³ per day of maximum dispatch capacity, 720,000 m³ of tanks at Punta Colorada and 150,000 m³ at Allen, the loading terminal at 1,500 units of value and each single-point mooring at 500. The first payment only arises sixty days after start-up, so it has not accrued yet verif · May 26, 2025
Base: Formula based on length, transport capacity, stored volume, loading terminal and loading points, in units of value
Who it goes to: the province
Ley M 3.266 and Decreto 656/04; Acta Acuerdo art. five point 5.5 and Annex III
Port public domain use fee estim · May 26, 2025+
Not charged yet: it becomes payable only once the port concession is granted. With the parameters the agreement itself declares, at maximum capacity it would come to around USD 14 million a year estim · May 26, 2025
Base: Per cubic metre dispatched, at a unit fee of 0.44 dollars
Who it goes to: the province
Acta Acuerdo art. five point 5.3 and Annex III

Who promised what

Who promised what, with a date and with how to check it. We record them whatever the political colour.

pendiente2
parcial2
4 promesas
pendienteVMOS S.A. and its shareholders · First crude export in early 2027, with commercial start-up at the close of the fourth quarter of 2026 verif · Aug 10, 2026 +
project owner · 2026-08-10
How it is checked: With the first vessel loaded at Punta Colorada and with YPF's quarterly report to the SEC
pendienteVMOS S.A. · Completing the minimum investment amount in computable assets before 31 December 2028, with a 20% milestone in the first two years from notification verif · Dec 31, 2028 +
project owner · 2025-03-21
How it is checked: It is overseen by the Secretaría de Energía as mandated by article 8 of the resolution. Failing it is treated as undue enjoyment of the benefits and requires returning them with interest
parcialVMOS S.A. · Paying Río Negro USD 40 million a year for thirteen years as a Community Contribution, on top of the initial USD 60 million bond prob · Feb 2026 +
project owner · 2025-05-26
How it is checked: Each payment falls due before 28 February. The provincial Contaduría General must report the allocation of the funds within 90 days of each year's close
parcialGovernment of Río Negro · That energy development leaves Río Negro suppliers behind: awarded companies went from 14 to 48 between the first quarter of 2025 and that of 2026, with 70% provincial participation prob · Mar 31, 2026 +
province · 2026-06-26
How it is checked: With the roll of the Río Negro Suppliers Register and with the quarterly procurement reports

What changes in Río Negro if the project works

The first vessel loads in early 2027 and by the second half of that year the system moves around 550,000 barrels a day. That is the headline, and it is not what matters most here.

What changes in Río Negro is that the province gains an oil export terminal where before there was a beach and a town living off the memory of a closed mine. Sierra Grande stops being a place you drive through: Ley 5.594 requires 80% of the project's workers and suppliers to be based in the province, and that share also reaches contractors and subcontractors, which is where the buying actually happens. In the first quarter of 2026 the project bought $15,902 million from Río Negro suppliers, and the largest category was not engineering: it was staff transport, at $5,164 million, followed by catering at $4,059 million.

And there is a second shift almost nobody is watching. Construction ends, but the system starts: a marine terminal operating around the clock needs maintenance, tugs, diving, pipeline inspection, spill response and environmental monitoring for decades. That market does not exist on the Río Negro coast today and it has no owner yet.

What breaks itThat the crude does not show up in the committed volume. In 2023 several blocks that now have to fill the pipeline were registered with the Energy Secretariat almost entirely as resources, not reserves: Rincón de Aranda, on which Pampa backs its 50,000 barrels a day, had zero proved reserves.

Outlook to 2027, built on the verified data of this page and our analytical framework. We also publish what would invalidate it.

What could stall itrisks and how to track them

What could stall it

Each risk, with who or what could trigger it.

1 ambiental1 logistico1 regulatorio1 social1 tecnico5 riesgos
tecnicoThat the committed crude does not show up in the firm volumeShippers committed 490,000 barrels a day firm, but part of that backing sits in blocks that are not reserves yet. As of 31 December 2023 Rincón de Aranda, the block on which Pampa bases its 50,000 barrels, was filed with the Secretaría de Energía with zero proved reserves and 11 million barrels of contingent resources; through all of 2025 it produced around 9,400 barrels a day. prob · Dec 31, 2023 +
This is a risk with mitigation under way and in plain sight: in March 2026 Pampa filed a RIGI project of 259 new wells for USD 4,500 million on that same block prob · Dec 31, 2023
logisticoThe offshore front is the critical stretch and it has no slackThe first export requires at least two tanks and one single-point mooring in operation. The tanks need fourteen days of hydrostatic testing each and can only be tested once roofed; the moorings are manufactured abroad and installed by a vessel campaign with a narrow weather window. All of that happens between September and December 2026. prob · Jun 2026 +
The terminal is materially further behind than the project average, and that is where the schedule risk lives prob · Jun 2026
ambientalEnvironmental and social in the Golfo San MatíasThe terminal operates in a gulf with protected coastal-marine areas, and the environmental approval is in YPF's name and not VMOS's. The permit conditions —marine monitoring, guarantees, spill contingency plan— are not published in the provincial Boletín Oficial, so they cannot even be audited from outside. verif · Sep 29, 2022 +
The provincial law governing pipeline transport expressly bans oil prospecting and production inside the Golfo San Matías, and empowers the authority to suspend works without prior proceedings where there is a risk of imminent damage, with fines of up to 2,200 m³ of crude oil verif · Sep 29, 2022
socialPressure on Sierra GrandeA town of fewer than 9,000 people takes in works that at their peak moved thousands. The governor himself acknowledged a significant rise in rents, and the only available description of the local hospital dates from 2009. 22.3% of the department's households rent. verif · 2022 +
There is no published series of rental prices in Sierra Grande, Playas Doradas or Las Grutas: the increase is stated but without a single figure verif · 2022
regulatorioClash between the provincial local-content rule and the national regimeRío Negro requires by law 80% of workers and suppliers established in the province; the RIGI guarantees projects that join it that they will not face rules forcing them to buy local on worse-than-market terms, and its own floor is 20%. Which one governs VMOS is not settled in any public act. verif · Sep 29, 2022 +
Article 165 of Ley 27.742 declares null any provincial rule that limits or distorts the regime; article 8 of Ley 5.594 requires 80% unless a cause is substantiated verif · Sep 29, 2022

The permits the works need, and where each one stands.

obtained3
in progress1
4 permisos
Environmental impact

Resolución 380/2024 of the Río Negro Environment and Climate Change Secretariat approved the pipeline's environmental impact study. It is in the name of YPF S.A., not VMOS: the agreement with the province provides for the transfer of the permits but there is no instrument approving it verif · 2024

Public hearing

It was held on 17 August 2023 at the Vuta Mahuida gymnasium in Sierra Grande and 51 people spoke. It ran all day: it opened at 8 and closed at 19:50. Under provincial law it is consultative and non-binding, and the official statement declares neither approval nor rejection prob · Aug 17, 2023

Transport licence

The certificate from the National Registry of Hydrocarbon Carriers, Operator category No. 58, is what allows VMOS to build the pipeline. It was granted on 6 February 2025 with expiry in July of that same year, and its renewal is not published verif · Feb 6, 2025

Water use

Two permits from the Provincial Water Department: Resolución 513/2025 for the terminal and the coastal pipeline, and Resolución 768/2025 for the Allen head station. Both cover construction, not operation verif · Sep 19, 2025

How to tell whether it is advancing

Observable facts that show whether the project is advancing, and where to look for each.

trimestralConstruction progress and first crude date+
Where: YPF's quarterly reports to the SEC (form 6-K). They are the only exchange-filed source that publishes the progress percentage with a date
It is the source that settles it when the press and the operator disagree: in July 2026 the press said 73% and the 6-K said 80%
eventoInstallation of the first single-point mooring+
Where: DOF Group ASA filings to the Oslo exchange and port press from San Antonio Este
It is the milestone that unlocks the first export, together with two tested tanks. Arrival is not installation: they are two different things and the sources mix them up
eventoRenewal of the carrier certificate+
Where: Registro Nacional de Transportistas de Hidrocarburos, Secretaría de Energía
Certificate No. 58, which authorises VMOS to build, expired in July 2025 and its renewal is not published
eventoWater permit for the operation+
Where: Boletín Oficial of Río Negro, resolutions of the Departamento Provincial de Aguas
The two permits in force cover construction only and lapse if the purpose changes. Operating the terminal requires a new permit, and that filing has to appear before the first export
trimestralPurchases from Río Negro suppliers+
Where: Quarterly reports by the Government of Río Negro on energy-sector suppliers
It is the only public series that measures whether local content is being met. Look at the breakdown by category, not the total: that is where you see what the project is buying now
eventoAccounting for the Community Contribution+
Where: The provincial Budget Law and the report the Contaduría General must send VMOS within 90 days of each year's close
The first one falls due on 31 March 2027 and is the first time promised can be checked against allocated

How we verified thisthe act, the gaps and the sources

The RIGI act, in detail

Accession date

Mar 6, 2025 verif · Mar 6, 2025

Date of the act

Mar 20, 2025 verif · Mar 20, 2025

Publication in the Boletín Oficial

Mar 21, 2025 (notice No. 17090/25, First Section) verif · Mar 21, 2025

The act’s articles, in detail

7 facts on the commitment
Investment commitment

20 % of the minimum investment amount, to be evidenced during the first and second year from notification of the resolution verif · Mar 21, 2025

Base it is calculated on

The 20% is calculated on the minimum investment amount the regulation sets for a Long-Term Strategic Export Project, not on VMOS's own investment. That minimum is USD 2,000 million, so the two-year milestone is around USD 400 million. It should not be read as an advantage: VMOS's subsector — oil and gas transport and storage — has a minimum of USD 300 million under the ordinary regime, where the required share is 40%, that is USD 120 million. Entering as a strategic project raises the bar for those two years, it does not lower it. estim · Mar 21, 2025

Deadline for the commitment

31 December 2028 to complete the minimum investment amount. VMOS declared a plan that front-loads almost all of it: USD 1,318 million in the first year and USD 1,123 million in the second. verif · Dec 31, 2028

Total investment declared in the act

Between USD 2,900 and USD 3,200 million USD million (declared by the applicant) verif · Mar 21, 2025

Assets computable under the regime

2.486 USD million recognised as computable assets under the RIGI verif · Mar 21, 2025

Vehículo de Proyecto Único

VMOS S.A., tax ID 30-71871335-4, registered at Ingeniero Enrique Butty 235, Ground Floor, Office 1, Buenos Aires City. It was created as a single-shareholder company (VMOS S.A.U.) and converted into a corporation on 13 December 2024, recorded with the corporate registry on 24 January 2025. There is a second entity worth not confusing: operations under the regime run through RIGI - VMOS S.A., tax ID 30-71890264-5, the separate tax identification that article 10 of the resolution ordered ARCA to create. verif · Mar 21, 2025

Who oversees compliance

The national Energy Secretariat, as assigned by article 8 of the resolution verif · Mar 21, 2025

How much it commits to invest, and how it pays for it

6 facts on the investment
Stage 1

1.333 USD million verif · Mar 21, 2025

Stage 2

1.153 USD million verif · Mar 21, 2025

First year

1.318 USD million verif · Mar 21, 2025

Second year

1.123 USD million verif · Mar 21, 2025

How it is financed

An international syndicated loan of USD 2,000 million signed on 8 July 2025, five-year term at SOFR plus 5.50%, covers around 70% of the project's capital; the remaining 30% comes from the shareholders. As of 31 December 2025 the banks had disbursed USD 820 million verif · Dec 31, 2025

Real estate

Four properties for USD 2.28 million in total, within the 15% cap set by law. That is 0.09% of the computable investment verif · Mar 21, 2025

What the regime gives in return

4 benefits of the regime
Category

Long-Term Strategic Export Project (PEELP), Oil and Gas sector, transport and storage of liquid and gaseous hydrocarbons verif · Mar 21, 2025

Stability

Thirty years of tax, customs, foreign exchange and regulatory stability counted from the date of adherence, that is from 6 March 2025 verif · Mar 6, 2025

Foreign currency

VMOS did NOT request the free availability of export proceeds, and so it does not have it. It is the most sought-after foreign exchange incentive in the regime and article 11 of the resolution expressly excludes it verif · Mar 21, 2025

Local content

The regime requires filing a local supplier development plan with a floor of 20% of the amount earmarked to pay suppliers of goods and works, sustained through construction and operation. VMOS filed one, but the plan is not public: the resolution mentions it once and without a single figure of its own. The law adds an escape clause worth knowing before complaining: the commitment applies «provided that local supply is available and on market terms as to price and quality» verif · Mar 21, 2025

What we could not confirm

There are 11 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01The conditions attached to the environmental permit+

Río Negro's Secretaría de Ambiente y Cambio Climático does not publish its environmental impact resolutions in the Boletín Oficial. We know the act's number —Resolución 380/2024— because a later decree cites it, but not its exact date, nor its text, nor its scope, nor a single one of its conditions: marine monitoring, guarantees, spill contingency plan, reporting obligations.

What would close itThe complete file 152387/1943, or the digital file 112015-SAYCC-2023 that the Secretaría itself published at the time
H-02How many people stay on once construction ends+

No source publishes the system's permanent operating headcount. Every figure in circulation is a construction figure: 2,000 at peak according to the contractor, more than 5,000 according to the province, 10,000 from the governor. The official RIGI register declares 3,108 direct and indirect jobs without distinguishing the stage.

What would close itThe operations chapter of the terminal's environmental impact study, which by regulatory format is the document where it should be
H-03What VMOS committed to in its supplier development plan+

The plan exists and is identified as document RE-2024-126056639-APN-SCEYM#MEC, but it is not public: the resolution mentions it once and without a single figure of its own, and the official RIGI portal only publishes aggregates. We do not know whether it committed to more than the legal floor of 20%, nor with what breakdown, nor on what base amount.

What would close itA freedom-of-information request to the Ministerio de Economía citing that document and its file
H-04The names of the Río Negro companies under contract+

The province publishes the aggregate —48 companies awarded in the sector, 70% from Río Negro, $15,902 million purchased in one quarter— but not the list. The provincial register does not expose a searchable roll and the chambers have not released it either. We have a single Río Negro company with a contract confirmed by name.

What would close itThe roll of the Río Negro Suppliers Register, or the supplier lists of the four main contractors
H-05What was left out of the computable assets+

Between the declared total investment and what the State recognises as computable there is a gap of between USD 414 and 714 million, and the breakdown is not published. Resolución 302/2025 has no annex: it is eight pages ending at the foot of the notice.

What would close itFile EX-2024-126061655-APN-SCEYM#MEC, through a freedom-of-information request
H-06How much water the project consumes+

The permits are there, with their source and their maximum authorised flow, but there is no published figure for actual consumption: neither for construction nor for operation. And operating consumption is a structural gap, not a search failure: the permits in force cover construction only.

What would close itThe flow-meter sworn statements VMOS files with the Departamento Provincial de Aguas
H-07Whether Río Negro actually collected the USD 60 million bond and the first annual instalment+

The commitment is in point 5.2 of the Acta Acuerdo ratified by Ley 5782 —USD 60 million initial bond plus USD 40 million a year for thirteen years, falling due before 28 February each year— and the province reported the first two receipts as collected. But neither has a public primary source: what exists is the provincial statement, not an act evidencing the receipt.

What would close itThe Contaduría General's report on the allocation of the funds, which the agreement itself requires to be issued within 90 days of each year's close.
H-08What the USD 60 million of the bond was spent on+

What exists are announcements in the future tense, not an accounting of executed spending. No administrative act allocates the bond line by line, and in the province's 2025 Investment Account there is not a single traceable line by name: zero mentions of VMOS, of the bond or of the pipeline across 111 pages.

What would close itThe provincial Budget Law, which is where the agreement itself requires the allocation of the funds to be included
H-09How the Punta Colorada Terminal is powered+

The regulator's act covers the Allen and Chelforó pump stations, not the terminal. For the terminal there is no power rating, no voltage, no substation, no supplier, no transmission line works. And the electrical filing is in YPF's name, not VMOS's, so searching by the project's name does not find it.

What would close itENRE files or Boletín Oficial notices in the name of YPF S.A. or Transcomahue for Punta Colorada
H-10The capacity of the Sierra Grande hospital+

The only description of staffing that exists dates from 2009 and sits in the explanatory notes of a bill that was never passed. Beds in service, emergency cover and shifts: no data at any date. It is the corridor's most concrete local pressure and the least measured.

What would close itData from Río Negro's Ministerio de Salud or from the relevant health district
H-11Rental prices in the corridor+

There is no published series with a dated source and a method for Sierra Grande, Playas Doradas or Las Grutas. The increase is stated by the governor himself, but without a single figure. What does stand as a durable baseline is the tenure structure: 22.3% of the department's households rent, according to the 2022 census.

What would close itA price series with a stated method, or the register of lease contracts

Frequently asked questions

Does VMOS start in Neuquén?Noverif+

The approved project runs from Allen to Punta Colorada, both points inside Río Negro, and it is 437 kilometres long. The crude does come from Vaca Muerta, but it reaches Allen through other pipelines that are not part of this project.

How much money does VMOS leave in Río Negro?A one-off bond of USD 60 million, plus USD 40 million a year for thirteen years, plus a control fee of USD 1.05 million a year, plus the environmental fee and the port fee once the system operatesverif+

5% of the bond goes to the municipality of Sierra Grande.

How much do I have to buy from Río Negro suppliers if I work on the project?Ley provincial 5.594 requires no less than 80% of workers and suppliers established in Río Negro, and it also reaches contractors and subcontractorsverif+

The RIGI, for its part, sets a floor of 20% for local suppliers. Which of the two regimes prevails over a project that has joined is not settled in any public act.

When does the first vessel sail?In early 2027, according to what YPF told the market in August 2026verif+

It requires at least two tested tanks and one single-point mooring in operation.

Who owns VMOS?Nine oil groupsverif+

Only three publish their stake because they are the only listed ones: YPF 24.49%, Vista 10.20% and Pampa 10.20% at the close of 2025. Gas y Petróleo del Neuquén is the only Class B shareholder. None of them controls the company.

Who do I invoice if I sell a service?In most cases, the contractor and not the pipeline's owner: the large packages are held by Techint-SACDE, Milicic, AESA and OPS, and each builds its own chainverif+

If you invoice the company, check which one: VMOS S.A. has CUIT 30-71871335-4 and the operation under the regime runs through RIGI - VMOS S.A., CUIT 30-71890264-5.

How to read the seals →   verif primary source · prob primary source pending · unconf not sufficiently backed · estim our own calculation · thesis our reading
Fact sheet built on primary sources, with the gaps declared. Back to Río Negro