Despegue ← Projects Proyecto RIGI
The 31 projectsPROJECT ▾
Neuquén
YPF 'LLL Oil' (shale-oil mega-development)Pluspetrol - Bajo del Choique / La InvernadaTecpetrol - Los Toldos II EstePampa Energía - Rincón de ArandaTGS - Natural gas liquids (NGL) project, Tratayén - Bahía BlancaAmpliación Mega - natural gas liquids (NGL)
San Juan
Vicuña (Josemaría + Filo del Sol) — copper, gold and silverEl Pachón - copper, silver and molybdenum (Glencore)Los Azules — copper cathodes (McEwen Copper)Gualcamayo — Deep Carbonates (DCP): gold and silver (Minas Argentinas)Leaching Phases 8 and 9 expansion — Veladero Mine (gold)
Catamarca
Agua Rica / MARA — copper, gold, silver and molybdenum (Glencore)Salar Tres Quebradas (3Q), stage 2 — lithium carbonate (LIEX/Zijin)Fénix — Phase 1B Expansion: lithium carbonate (Minera del Altiplano / Rio Tinto)Hombre Muerto Oeste (HMW) — lithium carbonate (Galan)
Río Negro
Argentina LNG (YPF, Eni and XRG)Southern Energy - floating LNG (Argentina LNG, Hilli phase)Vaca Muerta Oleoducto Sur (VMOS)San Matías Gas Pipeline (San Matías Pipeline S.A.) - evacuation of Vaca Muerta gas to the Atlantic
Salta
Pozuelos-Pastos Grandes (PPG)Rincón Project — lithium carbonate (Rio Tinto)Diablillos — gold and silver (Salta/Catamarca)Sal de Oro II — lithium carbonate (POSCO)
Buenos Aires
Fértil Pampa — urea and ammonia plant in Bahía BlancaSidersa Argentine Steel Project — long steel productsOlavarría Wind Farm (P.E. Olavarría) — wind generation (GEAR I / PCR + ArcelorMittal Acindar)
Mendoza
PSJ Cobre Mendocino (San Jorge) — copper and goldEl Quemado Solar Park and Annexes — photovoltaic generation (Luz del Campo SA / YPF Luz)
Jujuy
Cauchari-Olaroz Expansion — lithium carbonate (Exar)
La Pampa
Perito Moreno Gas Pipeline expansion (ex-GPNK) - TGS
Santa Fe
Timbúes Multipurpose Terminal — port infrastructure (Terminal Timbúes SA)
ESEN
up to date · reviewed Oct 15, 2026
Energy - Oil and Gas (shale)/Neuquén
approved

Tecpetrol - Los Toldos II Este

announced investment
6.400USD M
operator
Tecpetrol 90% / GyP 10%
approving act
Resolución 1771/2026
what it will need
2procurement fronts

Development of ~70,000 bbl/d, ~380 wells, 35-year concession. 10% carry for GyP. The works include a Central Processing Facility (CPF), 50 MW of on-site power generation, 40,000 HP of compression, gas and crude evacuation pipelines and water intake systems.

Summary
share among the 24 approved RIGI projectstotal USD 42,134 M
Tecpetrol15.2%
the other 23USD 35,734 M
what stage it is atunder construction verif Apr 17, 2026 ↗

How to supply it

what we have for a supplier, and how to request it

What we have on this project for a supplier

How to get in
3 registration routes, with their status · 2 requirements with the rule that sets each one · 5 steps in order, with their timing

Who decides the purchase, who you invoice and where a new supplier registers.

What it buys and when
3 phases, with what each one buys · 1 happening now

Which lines each phase buys and when the window opens for each one.

What it is missing
2 services it will need and has no supplier for yet

Which they are, why it will need them and who could provide them.

Who is already in
1 company with a contract on the works · 1 with their own purchasing door

Who they are, what each one does and how to sell to them.

All of this is surveyed and verified against its source. Crossed with what you sell —which of them your products suit, how to reach it and when— it is in your company report. Request the report

Does your company fit into Tecpetrol?

We cross what you manufacture or do against the 3 phases of this project and tell you which ones you fit into and when each one buys. Two pages, with the evidence behind them.

Where my company can get in

The project

what it is, the route, the owners, the works and the contractors

Where it runs and how much it can move

Area

Vaca Muerta North Hub, near Rincon de los Sauces, province of Neuquen prob Aug 19, 2026 ↗

Central Processing Facility (CPF)

One plant to be built, of 70,000 barrels of oil a day and 3,600,000 m³ of gas a day verif unit prob Aug 19, 2026 ↗

On-site power generation

50 MW (generation system to be built) prob Aug 19, 2026 ↗

Compression

40.000 HP to be installed prob Aug 19, 2026 ↗

Evacuation

Gas and crude evacuation pipelines works to be built, no published length prob Aug 19, 2026 ↗

Water

Water intake systems works to be built, no published flow rate prob Aug 19, 2026 ↗

Who owns it

Tecpetrol 90% / GyP 10% verif Apr 1, 2026 ↗

The works, milestone by milestone

Oct 9, 2026RIGI resolution

The Official Gazette publishes Resolución 1771/2026 of the Ministry of Economy, which approves the adhesion to the RIGI as a PEELP (strategic long-term export project) with an adhesion date of Sep 9, 2026. Declared schedule: stage 1 from Nov 1, 2024 to Feb 28, 2027 (USD 1,635 M: central plant, oil pipeline, gas pipeline and 16 wells); stage 2 from Mar 1, 2027 to Jun 30, 2029 (USD 1,268 M: expansion of the plant to 70,000 barrels per day and 91 wells); stage 3 from Jul 1, 2029 to 2054 (USD 3,529 M: the last 273 wells).

Aug 19, 2026rigi announcement

The Minister of Economy announces that the Comité Evaluador approved the project's entry into the RIGI for USD 6.4 billion, with 3,100 direct and 4,800 indirect jobs and a planned output of 70,000 barrels a day.

Apr 17, 2026works progress

The basin's vice-president reports 30 % works progress, three drilling rigs, twelve wells able to produce, around 400 wells in the full development and a peak of 4,000 people.

Apr 6, 2026rigi application

The government of Neuquén announces the project's RIGI filing: USD 2.4 billion through 2028, a 90/10 split between Tecpetrol and Gas y Petróleo del Neuquén, around 380 wells, 70,000 barrels a day, a 35,000-barrel module in March 2027 and its doubling towards July 2027.

Jan 1, 2026drilling

The block's development drilling campaign begins; in April 2026 three rigs are working in the area.

Feb 4, 2025environmental study

The Phase 2 environmental impact study is signed, prepared by the consultancy Physis SAS: 85 new pads with an average of four wells each, three separation batteries, the early production facility, 10 disposal wells, the reinjection aqueduct, the gas lift network, the export pipeline to Auca Mahuida, medium-voltage power lines and internal roads.

Feb 1, 2025works start

Work on the central processing facility begins with Techint Ingeniería y Construcción, under an EPC contract on a «Cost + Fixed Fee» basis.

Dec 31, 2024environmental licence

The Environment Secretariat grants the Phase 1 environmental licence through Disposición DI-2024-549-E-NEU-SAMB#MERN: 15 pads, 3 disposal wells, flowlines, production gathering, export pipelines, fuel gas network, water intake and aqueduct, water wells with their distribution system, and power lines.

Aug 2, 2022amended pilot plan

Decreto 1530/2022 ratifies the block's amended pilot plan, which evacuates initial production through Chevron facilities at El Trapial Este with a pipeline to Battery 6, operated by Tecpetrol along its whole length. The recitals mention the contract with Chevron for treatment of gross production, crude transport and dispatch, water disposal and gas conditioning.

Jul 26, 2019provincial concession

Decreto 1392/2019 grants Gas y Petróleo del Neuquén the unconventional exploitation concession over Los Toldos II Este «for a term of thirty-five (35) years... from 11 May 2019», covering 77.8 km², and approves the joint venture contract with Tecpetrol signed on 5 June 2019.

Jul 26, 2019works commitment

The same decree sets the pilot plan: one vertical well later horizontalised and completed plus two horizontal wells within no more than two years, for around USD 38,000,000, plus infrastructure and other investment within no more than three years, for around USD 15,000,000. And it sets the payments to the Province: USD 2,825,000 in corporate social responsibility and USD 1,500,000 as a contribution to infrastructure programmes and works, both within ten business days of the decree being published.

What it leaves in Neuquén

jobs, works, taxes, promises and the outlook

How many jobs it creates

In construction

More than 3,100 jobs at peak construction prob Aug 19, 2026 ↗

The works that stay behind

The infrastructure that stays standing once the works end, with its size and its source.

Export pipeline from the central facility to Auca Mahuida

Productive
37,883.91

metres of 24-inch line, maximum flow of 330,000 barrels a day

the block and, through the connection with Oldelval at Auca Mahuida, the basin's trunk evacuation system

Verbatim from the technical sheet in the environmental study: API 5L X56 steel, 24 inches nominal and outside diameter, «Length (m) 37,883.91», origin «CPF LT2E», destination «Auca Mahuida – Oldelval – Transport Pipeline», «Maximum flow 330,000 bopd», no internal coating and three-layer external coating, 0.438-inch wall thickness, design and maximum allowable pressure of 97.8 kg/cm², operating pressure of 38 kg/cm², buried. Upstream it carries a custody transfer metering unit with calibration prover, flow computer and automatic sampler.

Central Processing Facility (CPF), with modularised treatment trains

Productive
no figurePhase 1: 2,385 m³/day of hydrocarbon, 708.8 m³/day of water and 250.4 thousand m³/day of gas · Phase 2: 4,770 m³/day of hydrocarbon, 708.8 m³/day of water and 500.9 thousand m³/day of gas

the block for the 35 years of the concession: it is the plant that separates and treats everything the wells produce

The design capacities are declared by phase in the environmental study: «Phase 1: 2,385 Sm3/d (Hydrocarbon) / 708.8 Sm3/d (Water) / 250.4 MSm3/d (Gas). Phase 2: 4,770 Sm3/d (Hydrocarbon) / 708.8 Sm3/d (Water) / 500.9 MSm3/d (Gas)». The second phase doubles hydrocarbon and gas treatment and leaves water unchanged.

85 drilling pads with their access roads

Productive
144

× 235 metres and 29,240 m² each, 2.48 km² in total, with 506,998.82 m³ of imported aggregate

the block: they are the platforms from which drilling and production run for the whole concession

Each PAD carries an average of four wells and an internal pit of 10 × 40 metres. The declared imported aggregate is 5,964.69 m³ per PAD and 506,998.82 m³ for all 85. thesis It is the best quantified quarry demand in the project.

Three separation batteries

Productive
no figureeach one 200 × 265 m (70,138 m² including its flare), with a 160 m³ API 650 oil tank —9,050 mm in diameter by 2,500 mm high— on a cemented 176 m³ containment bund 800 mm high, a knock-out drum and a flare sized for all the gas received, and four compressors of 1,500 kW each

the block: they gather and separate production from the pads before sending it on to the central plant

The three batteries separate water and hydrocarbons from the PADs' output before sending it on to the central plant. Each carries twelve skid-mounted units —low-pressure separator, compression skid, accumulator tank, booster pump, transfer pump, hydrate- and corrosion-inhibitor injection, high-pressure header metering, instrument air, fuel gas, flare knock-out drum and relief system— plus four 1,500 kW compressors fuelled by the wells' own gas, with room set aside for more machines. Between them the three consume 42,082.80 m³ of imported aggregate, 14,027.60 m³ each. Relief systems are designed to API 520 and 521, and the safety valves are certified to API 526 in pairs: one in service, one on standby.

Reinjection aqueduct and gas lift network

Water
no figuretwo internal field networks, within the Phase 2 scope; the length is not published in the scope

the block: the aqueduct carries produced water to the ten disposal wells and the gas lift network sustains output from mature wells

The reinjection aqueduct and the gas lift network appear among the Phase 2 facilities, alongside «10 disposal wells». thesis The aqueduct and the disposal wells handle produced water inside the area, without taking it out of the block.

Medium-voltage power lines across the field

Power
no figureinternal network in Phase 2; the route and the voltage are not published in the scope

the block: it is what allows production to be electrified rather than run on diesel generation at each location

The medium-voltage lines are within the Phase 2 scope and were already in the Phase 1 scope («power lines» in licence DI-2024-549). On-site generation declared by the operator for the project is 50 MW prob.

Pending · 2 blocks
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall it

risks and how to track them
Pending · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified this

the act, the gaps and the sources

The RIGI act, in detail

Pending

We have not looked for this project’s RIGI act in the Boletín Oficial.

What we could not confirm

There are 5 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01The project's OPERATIONS headcount, and the 4,800 indirect jobs in the minister's announcement+

The phase ambiguity is resolved: Tecpetrol's own thread of Aug 19 says "more than 3,100 jobs at peak construction", that is, construction, and that figure is already recorded. What no one has published is how many people stay on once the field is producing, which is the number that decides whether a town gains population or just a construction spike. The 4,800 indirect jobs are not broken down by phase in any source either.

What would close itResolución 1771/2026, which approved the project and appeared in the Official Gazette on Oct 9, 2026, does not include the headcount. A statement from the operator publishing it is needed.
H-02What Tecpetrol asks of a new supplier in money and in payment terms+

The suppliers page publishes the procedure and the reference standards, but not the detail of the 83 requirements, nor payment terms, nor minimum working capital, nor whether provincial roots carry weight. Without that, an SME knows where to knock but not whether it can afford to.

What would close itThe company's general purchasing terms and conditions, or the documented account of a supplier already qualified.
H-03The exact date of Disposición DI-2024-549 and its full text+

The Phase 1 environmental licence is known only through the transcription in the Phase 2 study: number, file and scope. The act itself is not published in the open and neither research pass found it.

What would close itThe disposition on the site of Neuquén's Environment Secretariat or in the provincial Official Gazette. It is where the conditions imposed on the contractor live, which in other projects in this dataset turned out to be the real barrier to entry.
H-04Who is building Phase 2: the 85 pads, the three batteries and the export pipeline+

The work is measured down to the metre in the environmental study, but the project's only published contractor is the EPC for the central facility. For the rest there is no public award, and the project says it coordinates between 700 and 800 companies without publishing the list.

What would close itThe project sheet on the builder's own site, or the report of a presentation to a local business chamber. The operator's supplier development programme does publish names at its events: the second edition, in March 2026, named ten small firms.
H-05How much aggregate is needed per year and where it comes from+

The study declares 506,998.82 m³ of imported aggregate for the 85 pads, but does not give the pace or the source quarry. Without that, an aggregate supplier knows the total volume and not whether the logistics work for them.

What would close itThe year-by-year drilling schedule the operator publishes in its presentations, or the corresponding quarry permit at the Environment Secretariat.
First step · free
The first read of your company

We look at what your company does and tell you whether we see a sign that it fits this market, with the evidence behind it. If we do not see one, we say so too and name the condition that would change it. One page as a dated PDF, within 48 working hours.

Not here for a company? Invest · Work (in Spanish) · Start a business (in Spanish) · Institutions
Page 1 of the example executive summaryOpen the report ↗A real analysis · a real company, open in full →
Ignacio Aredez
Analysis and curation: Ignacio Aredez
Head of Despegue
Method and track record →
  • 20+ years in technology, 15 of them in data and AI, for clients across Europe and the Americas
  • Certified in AI governance (ISO/IEC 42001)
  • Machine Learning (Google Cloud)
  • Registered expert with the European Commission
How to read the seals →
  verif primary source · prob primary source pending · unconf a source said it · estim our own calculation · thesis our reading · the date belongs to the datum, at the precision its source allows
This is not financial advice. The page is built on the act that approved the project and the source of every figure, with the gaps declared. What the company announces is published as an announcement, and what is our own reading is labeled as thesis. ← Back to Neuquén