Pampa Energía - Rincón de Aranda
The RIGI's first oil upstream project. Adhesion on 25-Jun-2026 (Minute 23 of the Evaluating Committee) and approval by Resolution 1025/2026 of the Ministry of Economy (Official Gazette 21-Jul-2026), PEELP category: the act approves USD 4,521M in computable assets across three stages through 2041, with 259 wells (50 + 70 + 139). Employment splits in two and the difference matters: 715 direct and 500 indirect jobs in CONSTRUCTION, and 62 direct and 456 indirect in OPERATION. Target plateau ~45,000 bbl/d by the end of 2027; in Q2-2026 the block produced 23.4 kbbl/d. The capex jump —from the USD 376M midstream application of Jul-2025 to the entire project— was enabled by Decree 105/2026, which brought onshore hydrocarbon production into the RIGI with a USD 600M floor: it was a change of SCOPE, not the securing of evacuation capacity.
The projectwhat it is, the route, the owners, the works and the contractors
Who owns it
Pampa Energía verif · Jan 1, 2026 ↗
The works, milestone by milestone
Resolucion 1025/2026 approving the accession is published: USD 4,521 M in computable assets, long-term strategic export category, 259 wells in three stages through 2041
The presidential press office announces the approval and publishes the employment breakdown: 715 + 500 in construction, 62 + 456 in operation
The RIGI Project Evaluating Committee meets and recommends approval (Acta N 23); it is also the legal accession date
Decreto 105/2026 brings onshore hydrocarbon exploration and production into the RIGI with a USD 600 M floor, and extends the accession deadline by one year
Pampa files its USD 376 M midstream application with the RIGI, through the Sucursal Dedicada Midstream RDA, for a processing plant
The block's development plan starts, with a drilling campaign and facilities
The province grants the Unconventional Production Concession (CENCH) over the CNQ 38 Rincon de Aranda area, 239.39 km2, for 35 years
Who already has a contract
We have not surveyed this project’s awards. A published contract with its source closes them.
How to supply itwhere to register, what they ask for and what they will buy
How to become a supplier
We have not built this project’s entry map. It is our gap, not a prohibition: it closes by opening the provincial register and the operator’s single window.
What it will buy, and when
Each phase buys different things at different times.
First stage - CPF, pipelines and 50 wells
en cursoUSD 1,159 M and 50 horizontal wells: central processing facility, oil pipelines and gas pipelines. This is the stage that pays today.
They are not buying any of this today. Open the phase to see the detail and arrive qualified the day it goes to tender.
What it will need and has no supplier for yet
Technical accreditation of computable assets before the Energy Secretariat
highThe resolution approving it does not approve and walk away: it requires accrediting, during the first and second year, an investment in computable assets equal to or above 20%, and reaching a floor of USD 2,000M before 1 July 2031, all under the supervision of the Energy Secretariat. On a project of USD 4,521M spread across three stages through 2041, each accreditation is recurring technical-accounting work -asset computation and valuation, documentary support, defence before the auditor- with a deadline written into the rule. It is not the same service as a supplier's registration agency: this sits on the RIGI holder's side, and today it is handled by Buenos Aires firms.
Land management and easements for 259 well pads over 17 years
mediumThe 259 committed wells do not arrive at once: 50 through 2028, another 70 through 2031 and 139 through 2041. Each one carries its pad, its access road and its gathering pipelines, and each is negotiated with surface owners and local communities. It is continuous fieldwork over seventeen years -survey, measurement, agreement, compensation, registration- with the particularity that the final third concentrates 54% of the wells: whoever positions now serves demand that triples. No niche on the map quantifies it and there is no local supplier of the right size; notaries and generalist firms absorb it.
Final disposal capacity for flowback, not just its treatment
mediumIn the basin, more than 95% of flowback ends up in disposal wells instead of being recycled, and the five plants in Añelo that concentrate treatment received 1,022,290 m3 in 2023 -35.2% more than the previous year- operating at their limit. A development of 259 new wells pours volume onto a system that is already saturated. The water and waste niche measures TREATMENT and reuse; the other half of the problem has no owner: drilling, permitting and operating the disposal capacity that this volume will need, with the environmental permit as the real bottleneck.
Fiscal metering and custody transfer of export-bound crude
mediumThe PEELP category commits the project to long-term exports, and the approved scope expressly includes treatment, storage and transport of the crude. Every volume crossing into export passes through fiscal metering and custody transfer: certified standards, traceable calibration and an independent third-party audit, because that number defines what is charged and what is taxed. Catamarca already has the niche measured for lithium; in Neuquén, with this project delivering into the export route, calibration is still resolved with laboratories from outside the province.
Get on board the takeoff
This week’s updates: proyectos RIGI, proveedores y datos verificados de Neuquén and new provinces as they launch. Free.
What it leaves in Neuquénjobs, works, taxes, promises and the outlook
How many jobs it creates
715 direct jobs and 500 indirect ones verif · Jun 30, 2026 ↗
62 direct jobs and 456 indirect ones verif · Jun 30, 2026 ↗
What it already pays in taxes and royalties
Item by item, with the rule that sets it. A rate is not the same as what is collected, nor what is received the same as what is projected.
Hydrocarbon royalty verif · Jul 31, 2023 ↗+
Hydrocarbon royalty - top rate from 20 Jul 2027 verif · Jul 20, 2027 ↗+
Area Extension Bonus verif · Jul 31, 2023 ↗+
Corporate Social Responsibility Contribution verif · Jul 31, 2023 ↗+
- The works that stay behind — We have not surveyed this project’s permanent works. A published size with its source closes them.
- Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.
What could stall itrisks and how to track them
- What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
- How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.
How we verified thisthe act, the gaps and the sources
The RIGI act, in detail
Jun 25, 2026 verif · Jul 21, 2026 ↗
Jul 20, 2026 verif · Jul 20, 2026 ↗
Jul 21, 2026 verif · Jul 21, 2026 ↗
The act’s articles, in detail
8 facts on the commitment
2.000 verif · Jul 21, 2026 ↗
1.099 verif · Jul 21, 2026 ↗
2031-07-01 verif · Jul 21, 2026 ↗
4.521 verif · Jul 21, 2026 ↗
Pampa Energía S.A. - Sucursal Dedicada Proyecto RDA, tax ID 30-71901911-7, registered at Maipú N° 1, Buenos Aires City. verif · Jul 21, 2026 ↗
Jun 25, 2026 verif · Jun 25, 2026 ↗
The Energy Secretariat verif · Jul 21, 2026 ↗