Despegue Proyectos Proyecto RIGI ESEN
up to date · reviewed Aug 19, 2026
Energy - photovoltaic power generation (305 MW)/Mendoza
approved

El Quemado Solar Park and Annexes — photovoltaic generation (Luz del Campo SA / YPF Luz + EMESA)

total investment in the act
211,6USD M

The first project to enter the RIGI: a 305 MW photovoltaic solar park (31.4% capacity factor) in Jocolí (Las Heras, Mendoza), developed by Luz del Campo SA (YPF Luz + EMESA). It is built in two stages; the first installs 200 MW over 350 ha with bifacial panels. It marks the debut of the regime and of one of the few RIGI investments in Mendoza.

operator
Luz del Campo S.A.
approving act
Resolución 1/2025
what it will need
2procurement fronts
Summary
share among the 22 approved RIGI projects we tracktotal USD 33,041 M
El Quemado Solar Park and Annexes0.6%
the other 21USD 32,829 M

The projectwhat it is, the route, the owners, the works and the contractors

Who owns it

Luz del Campo S.A. (VPU, CUIT 30-71765521-0); joint venture of YPF Luz and EMESA (a Mendoza energy company) per press reports verif · Jan 8, 2025

We have not worked on this yet · 2 blocks
  • The works, milestone by milestone — We have not built this project’s timeline. Dated milestones with their source close it.
  • Who already has a contract — We have not surveyed this project’s awards. A published contract with its source closes them.

How to supply itwhere to register, what they ask for and what they will buy

What it will need and has no supplier for yet

tesisOur own reading of the project, not company-reported data.

Solar farm assembly (pile driving, panel installation, DC/AC electrical works)

high

A 305 MW farm across hundreds of hectares demands labour- and structure-intensive assembly: solar mounting and electrical works contractors.

Supplied bysolar EPC / electrical assembly

Farm O&M and grid connection (transformation, evacuation line)

medium

Once operating it requires module/inverter maintenance and the connection works to the SADI grid: O&M services and electrical EPC.

Supplied byO&M services / electrical EPC
We have not worked on this yet · 2 blocks
  • How to become a supplier — We have not built this project’s entry map. It is our gap, not a prohibition: it closes by opening the provincial register and the operator’s single window.
  • What it will buy, and when — We have not built this project’s phase → demand chain: its schedule still has to be crossed with the province’s catalogue of markets and trades.
Weekly newsletter · free

Get on board the takeoff

This week’s updates: proyectos RIGI, proveedores y datos verificados de Mendoza and new provinces as they launch. Free.

no spam we read every one
Which are you?
What are you looking for?
Tell us more
Your provinces empty = all
pick one or more

What it leaves in Mendozajobs, works, taxes, promises and the outlook

We have not worked on this yet · 3 blocks
  • The works that stay behind — We have not surveyed this project’s permanent works. A published size with its source closes them.
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall itrisks and how to track them

We have not worked on this yet · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified thisthe act, the gaps and the sources

The RIGI act, in detail

Accession date

Dec 16, 2024 verif · Jan 8, 2025

The act’s articles, in detail

2 facts on the commitment
Deadline for the commitment

30 January 2027 to complete the minimum investment amount. verif · Jan 30, 2027

Vehículo de Proyecto Único

Luz del Campo S.A., tax ID 30-71765521-0, registered at Macacha Güemes 515, Floor 3, Buenos Aires City. verif · Jan 8, 2025

How to read the seals →   verif primary source · prob primary source pending · unconf not sufficiently backed · estim our own calculation · thesis our reading
Fact sheet built on primary sources, with the gaps declared. Back to the RIGI pipeline