Despegue ← Projects Proyecto RIGI
The 31 projectsPROJECT ▾
Neuquén
YPF 'LLL Oil' (shale-oil mega-development)Pluspetrol - Bajo del Choique / La InvernadaTecpetrol - Los Toldos II EstePampa Energía - Rincón de ArandaTGS - Natural gas liquids (NGL) project, Tratayén - Bahía BlancaAmpliación Mega - natural gas liquids (NGL)
San Juan
Vicuña (Josemaría + Filo del Sol) — copper, gold and silverEl Pachón - copper, silver and molybdenum (Glencore)Los Azules — copper cathodes (McEwen Copper)Gualcamayo — Deep Carbonates (DCP): gold and silver (Minas Argentinas)Leaching Phases 8 and 9 expansion — Veladero Mine (gold)
Catamarca
Agua Rica / MARA — copper, gold, silver and molybdenum (Glencore)Salar Tres Quebradas (3Q), stage 2 — lithium carbonate (LIEX/Zijin)Fénix — Phase 1B Expansion: lithium carbonate (Minera del Altiplano / Rio Tinto)Hombre Muerto Oeste (HMW) — lithium carbonate (Galan)
Río Negro
Argentina LNG (YPF, Eni and XRG)Southern Energy - floating LNG (Argentina LNG, Hilli phase)Vaca Muerta Oleoducto Sur (VMOS)San Matías Gas Pipeline (San Matías Pipeline S.A.) - evacuation of Vaca Muerta gas to the Atlantic
Salta
Pozuelos-Pastos Grandes (PPG)Rincón Project — lithium carbonate (Rio Tinto)Diablillos — gold and silver (Salta/Catamarca)Sal de Oro II — lithium carbonate (POSCO)
Buenos Aires
Fértil Pampa — urea and ammonia plant in Bahía BlancaSidersa Argentine Steel Project — long steel productsOlavarría Wind Farm (P.E. Olavarría) — wind generation (GEAR I / PCR + ArcelorMittal Acindar)
Mendoza
PSJ Cobre Mendocino (San Jorge) — copper and goldEl Quemado Solar Park and Annexes — photovoltaic generation (Luz del Campo SA / YPF Luz)
Jujuy
Cauchari-Olaroz Expansion — lithium carbonate (Exar)
La Pampa
Perito Moreno Gas Pipeline expansion (ex-GPNK) - TGS
Santa Fe
Timbúes Multipurpose Terminal — port infrastructure (Terminal Timbúes SA)
ESEN
up to date · reviewed Oct 15, 2026
Oil and gas - natural gas liquids (NGL)/Neuquén
approved

Ampliación Mega - natural gas liquids (NGL)

total investment in the act
365USD M
operator
Compañía Mega S.A. Sucursal Dedicada
approving act
Resolución 1381/2026
what it will need
3procurement fronts

Expansion of the MEGA Industrial Complex to add 1,500 tonnes per day of natural gas liquids on top of a current capacity of 5,500. It touches three fronts: new facilities at the Loma La Lata separation plant (Neuquén), more transport capacity on the pipeline that crosses Neuquén, Río Negro, La Pampa and Buenos Aires, and the expansion of the Bahía Blanca fractionation plant. The resolution sets that 60% of the amount earmarked for suppliers, goods and infrastructure works goes to local suppliers, against the 20% the regime requires. Commercial operation of the expansion starts, per the instrument, on February 28, 2029, with a declared useful life of 18 years. Official portal: 792 jobs (direct and indirect).

Summary
share among the 24 approved RIGI projectstotal USD 42,134 M
Ampliación Mega0.9%
the other 23USD 41,769 M
what stage it is atpre-construction prob Jun 30, 2026 ↗

How to supply it

what we have for a supplier, and how to request it

What we have on this project for a supplier

How to get in
2 registration routes, with their status · 5 requirements with the rule that sets each one · 5 steps in order, with their timing

Who decides the purchase, who you invoice and where a new supplier registers.

What it buys and when
2 phases, with what each one buys · 1 happening now

Which lines each phase buys and when the window opens for each one.

What it is missing
3 services it will need and has no supplier for yet

Which they are, why it will need them and who could provide them.

All of this is surveyed and verified against its source. Crossed with what you sell —which of them your products suit, how to reach it and when— it is in your company report. Request the report

Does your company fit into Ampliación Mega?

We cross what you manufacture or do against the 2 phases of this project and tell you which ones you fit into and when each one buys. Two pages, with the evidence behind them.

Where my company can get in

The project

what it is, the route, the owners, the works and the contractors

Who owns it

Compañía Mega S.A. Sucursal Dedicada (CMSD, tax ID 30-71932893-4) verif Aug 26, 2026 ↗

The works, milestone by milestone

Aug 26, 2026official gazette

Resolución 1381/2026 is published in the Official Gazette verif.

Aug 25, 2026resolution

The Ministerio de Economía signs Resolución 1381/2026 approving the accession.

Jul 28, 2026rigi accession

The legal RIGI adhesion date set by the act, 29 days before publication verif. It is the date from which the regime's deadlines counted from adhesion start to run thesis.

Mar 18, 2026filing

Compañía Mega S.A. Sucursal Dedicada files its RIGI accession request for the expansion of a pre-existing project that had not joined the regime.

What it leaves in Neuquén

jobs, works, taxes, promises and the outlook

The works that stay behind

The infrastructure that stays standing once the works end, with its size and its source.

New separation and fractionation capacity for natural gas liquids at the MEGA industrial complex

Productive
1,500

additional tonnes per day on top of a current capacity of 5,500, that is, more than 500,000 tonnes a year of ethane, propane, butane and natural gasoline

Neuquén's gas chain, which stops flaring or exporting as gas what is now separated out, and the petrochemical industry of Bahía Blanca, which takes the ethane

The resolution approving the RIGI adhesion states the purpose: to expand natural gas liquids production capacity by 1,500 tonnes per day on top of a current capacity of 5,500 tonnes per day verif. In annual terms that is more than 500,000 tonnes of ethane, propane, butane and natural gasoline, and eight out of every ten tonnes of that additional volume are exported through Bahía Blanca; the rest is mostly ethane for the local petrochemical industry prob.

Added transport capacity on the Loma La Lata – Bahía Blanca liquids pipeline

Productive
no figurea route crossing four provinces —Neuquén, Río Negro, La Pampa and Buenos Aires—; the capacity increase is not published in tonnes or in new kilometres

the entire liquids chain leaving Neuquén for the petrochemical hub and the port of Bahía Blanca

This is the second of the three fronts the act declares: the Loma La Lata separation plant in Neuquén, the «Loma La Lata – Bahía Blanca» pipeline crossing Neuquén, Río Negro, La Pampa and Buenos Aires, and the Bahía Blanca fractionation plant. The act declares the three fronts but breaks down neither the investment nor the capacity of each one.

Pending · 2 blocks
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall it

risks and how to track them
Pending · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified this

the act, the gaps and the sources

The RIGI act, in detail

Administrative file number

EX-2026-28242295- -APN-SCEYM#MEC verif Aug 26, 2026 ↗

Accession date

28 July 2026 verif Jul 28, 2026 ↗

Date of the act

25 August 2026 verif Aug 25, 2026 ↗

Publication in the Boletín Oficial

26 August 2026 verif Aug 26, 2026 ↗

The act’s articles, in detail

7 facts on the commitment
Local content set by the act

60 % of the amount earmarked for suppliers that goes to LOCAL suppliers verif Aug 26, 2026 ↗

What that local content is calculated on

The entire investment amount earmarked for paying suppliers, goods and infrastructure works, during the project's construction and operation stages verif Aug 26, 2026 ↗

Deadline for the commitment

1 October 2027 verif Aug 26, 2026 ↗

Total investment declared in the act

365 USD million - total investment in the instrument (USD 365,398,669) verif Aug 26, 2026 ↗

Assets computable under the regime

359 USD million - assets computable under the regime (USD 359,164,361) verif Aug 26, 2026 ↗

Vehículo de Proyecto Único

Compañía Mega S.A. Sucursal Dedicada (CMSD), tax ID 30-71932893-4. verif Aug 26, 2026 ↗

Date the application was filed

18 March 2026, as the expansion of a pre-existing project not adhered to the regime verif Mar 18, 2026 ↗

What we could not confirm

There are 5 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01How the investment splits across the three work fronts (separation, pipeline, fractionation).+

The resolution declares the total and the computable amount, not their breakdown by front.

What would close itThe investment schedule by stage that the company files with the RIGI Coordination Unit, or a statement from Compañía Mega itself.
H-02How much of the additional 1,500 tonnes a day is separated in Neuquén and how much is fractionated in Bahía Blanca.+

Neither the resolution nor the official portal breaks capacity down by plant.

What would close itThe project's technical report or Compañía Mega's production balance.
H-03When each front goes to tender and for how much.+

The act sets the minimum investment deadline (1 Oct 2027) and the commercial start date (28 Feb 2029), but not the contracting schedule.

What would close itCompañía Mega's procurement register or its calls to suppliers; there is no public single window identified for this project today.
H-04The 792 direct and indirect jobs, and how they split between construction and operation.+

The figure comes from the official portal, which publishes it as a single combined number. The resolution carries NO employment figure: it says «estimación del empleo directo e indirecto del Proyecto con integración local» without a number. The «800 jobs» the Ministerio de Economía tweeted on 26 and 28 August are that same figure, rounded.

What would close itThe employment study the company filed with its application, which is not public.
H-05Who is building it: not a single contractor has been made public on any of the three work fronts+

Neither the resolution, nor the official RIGI portal, nor the project's own publicity names a single construction company. The resolution sets out the year-by-year investment plan but not the contracting schedule, and the company publishes no supplier gateway for this project. ⛔ And there is an easy mistake to avoid here: the new natural gas liquids fractionation train in Bahía Blanca that the company COMPLETED in May 2026 is a different job —USD 260 million—, not this one, which is roughly USD 360 million and has not started.

What would close itAn award announcement from the company, the project sheet on the winning contractor's own site, or the report of a presentation to a business chamber in Neuquén or Bahía Blanca, which is where the civil works contractors of other projects in this dataset turned up.
First step · free
The first read of your company

We look at what your company does and tell you whether we see a sign that it fits this market, with the evidence behind it. If we do not see one, we say so too and name the condition that would change it. One page as a dated PDF, within 48 working hours.

Not here for a company? Invest · Work (in Spanish) · Start a business (in Spanish) · Institutions
Page 1 of the example executive summaryOpen the report ↗A real analysis · a real company, open in full →
Ignacio Aredez
Analysis and curation: Ignacio Aredez
Head of Despegue
Method and track record →
  • 20+ years in technology, 15 of them in data and AI, for clients across Europe and the Americas
  • Certified in AI governance (ISO/IEC 42001)
  • Machine Learning (Google Cloud)
  • Registered expert with the European Commission
How to read the seals →
  verif primary source · prob primary source pending · unconf a source said it · estim our own calculation · thesis our reading · the date belongs to the datum, at the precision its source allows
This is not financial advice. The page is built on the act that approved the project and the source of every figure, with the gaps declared. What the company announces is published as an announcement, and what is our own reading is labeled as thesis. ← Back to Neuquén