Despegue ← Projects Proyecto RIGI
The 31 projectsPROJECT ▾
Neuquén
YPF 'LLL Oil' (shale-oil mega-development)Pluspetrol - Bajo del Choique / La InvernadaTecpetrol - Los Toldos II EstePampa Energía - Rincón de ArandaTGS - Natural gas liquids (NGL) project, Tratayén - Bahía BlancaAmpliación Mega - natural gas liquids (NGL)
San Juan
Vicuña (Josemaría + Filo del Sol) — copper, gold and silverEl Pachón - copper, silver and molybdenum (Glencore)Los Azules — copper cathodes (McEwen Copper)Gualcamayo — Deep Carbonates (DCP): gold and silver (Minas Argentinas)Leaching Phases 8 and 9 expansion — Veladero Mine (gold)
Catamarca
Agua Rica / MARA — copper, gold, silver and molybdenum (Glencore)Salar Tres Quebradas (3Q), stage 2 — lithium carbonate (LIEX/Zijin)Fénix — Phase 1B Expansion: lithium carbonate (Minera del Altiplano / Rio Tinto)Hombre Muerto Oeste (HMW) — lithium carbonate (Galan)
Río Negro
Argentina LNG (YPF, Eni and XRG)Southern Energy - floating LNG (Argentina LNG, Hilli phase)Vaca Muerta Oleoducto Sur (VMOS)San Matías Gas Pipeline (San Matías Pipeline S.A.) - evacuation of Vaca Muerta gas to the Atlantic
Salta
Pozuelos-Pastos Grandes (PPG)Rincón Project — lithium carbonate (Rio Tinto)Diablillos — gold and silver (Salta/Catamarca)Sal de Oro II — lithium carbonate (POSCO)
Buenos Aires
Fértil Pampa — urea and ammonia plant in Bahía BlancaSidersa Argentine Steel Project — long steel productsOlavarría Wind Farm (P.E. Olavarría) — wind generation (GEAR I / PCR + ArcelorMittal Acindar)
Mendoza
PSJ Cobre Mendocino (San Jorge) — copper and goldEl Quemado Solar Park and Annexes — photovoltaic generation (Luz del Campo SA / YPF Luz)
Jujuy
Cauchari-Olaroz Expansion — lithium carbonate (Exar)
La Pampa
Perito Moreno Gas Pipeline expansion (ex-GPNK) - TGS
Santa Fe
Timbúes Multipurpose Terminal — port infrastructure (Terminal Timbúes SA)
ESEN
up to date · reviewed Oct 3, 2026
Mining - Copper (with gold, silver and molybdenum as by-products)/Catamarca
submitted

Agua Rica / MARA — copper, gold, silver and molybdenum (Glencore)

announced investment
4.000USD M
operator
Minera Agua Rica LLC, Argentine Branch
what it will need
6procurement fronts

Catamarca's largest copper project and the largest capital investment in the province. MARA integrates the Agua Rica deposit (Andalgalá) with the plant, the concentrate pipeline and the infrastructure already built at Bajo de la Alumbrera, which stopped mining in 2018: reusing an existing plant is the project's best economics and, at the same time, its most contested environmental argument (the plan is to use Alumbrera's depleted pit as a tailings facility). Proven and probable reserves declared as of 30-Jun-2019 (100% basis): 1,105 Mt at 0.49% copper, 0.03% molybdenum, 0.21 g/t gold and 2.8 g/t silver; the 2025 RIGI release cites approximately 1,200 Mt at 0.47% copper, 0.20 g/t gold, 3.40 g/t silver and 0.03% molybdenum (measured and indicated, a different basis: do not add them up). Estimated mine life 27-28 years. Glencore declared more than 10,000 construction jobs and more than 2,500 operating jobs, but COMBINED with El Pachón: do not attribute them to Catamarca. While the big project waits, the restart of Alumbrera's remaining phases is moving ahead with a first equipment and maintenance contract of ~USD 250 M and a water concession cut back from 1,200 to 800 liters per second.

Summary
share among the 8 filed RIGI projectstotal USD 109,241 M
Agua Rica / MARA3.7%
the other 7USD 105,241 M
what stage it is atpre-construction verif Aug 5, 2026 ↗

How to supply it

what we have for a supplier, and how to request it

What we have on this project for a supplier

How to get in
2 registration routes, with their status · 6 requirements with the rule that sets each one · 7 steps in order, with their timing

Who decides the purchase, who you invoice and where a new supplier registers.

What it buys and when
3 phases, with what each one buys · 1 happening now

Which lines each phase buys and when the window opens for each one.

What it is missing
6 services it will need and has no supplier for yet

Which they are, why it will need them and who could provide them.

All of this is surveyed and verified against its source. Crossed with what you sell —which of them your products suit, how to reach it and when— it is in your company report. Request the report

Does your company fit into Agua Rica / MARA?

We cross what you manufacture or do against the 3 phases of this project and tell you which ones you fit into and when each one buys. Two pages, with the evidence behind them.

Where my company can get in

The project

what it is, the route, the owners, the works and the contractors

Who owns it

Minera Agua Rica LLC, Argentine Branch; 100% controlled by Glencore International AG since 31-Jul-2023 (previously Yamana Gold 56.25% / Glencore 25% / Newmont 18.75%). Pan American Silver retains a 0.75% NSR royalty on copper for the life of the mine. prob Aug 18, 2025 ↗

The works, milestone by milestone

Oct 2, 2026rigi announcement

The national Government announces that the Comité Evaluador approved Agua Rica's admission to the RIGI. According to the statement: USD 4,000 million of investment, with USD 771 million in the first two years; 200,000 tonnes of copper a year and exports of USD 2,167 million a year; the ore is processed at the Alumbrera plant, travels by slurry pipeline to Tucumán and by rail to the port of Rosario; up to 3,500 jobs in construction and 1,250 direct and 3,750 indirect jobs in operation; works from November 2027 and operation from October 2031.

Sep 8, 2026environmental report

MARA filed with the Mining Ministry of Catamarca the Environmental Impact Report (IIA) for the exploitation stage, which contemplates developing Agua Rica using Alumbrera's existing infrastructure. It is now under evaluation.

Aug 31, 2026local headcount

The project's headcount went from 1,109 jobs in January 2026 to 1,844 in August: +735 in eight months, a 66.3% rise. Of those 735 new jobs, 575 went to people from Catamarca, and on the total 1,484 of 1,844 are from Catamarca — 80.5%.

Aug 5, 2026feasibility engineering

Verbatim from Glencore's first-half results presentation: «Agua Rica feasibility engineering underway. Environmental permitting submission expected to be filed in the coming weeks. RIGI approval expected shortly thereafter». It is the only declared date for the environmental permit, and it comes without a day.

Jun 2, 2026Alumbrera restart

Glencore sets the restart of mining at Bajo de la Alumbrera —the old mine whose plant MARA will reuse— for 2 June 2026, with first production expected in the second half of 2027.

Aug 18, 2025RIGI filing

Glencore announces that it filed the RIGI adhesion applications for El Pachón and Agua Rica. Agua Rica enters at USD 4,000 M, the midpoint of a declared range of USD 3,500 to 4,500 M. The release says «has submitted applications»: it is a filing, not an approval.

What it leaves in Catamarca

jobs, works, taxes, promises and the outlook

How many jobs it creates

In construction

up to 3,500 jobs at the construction peak; neither of the two sources separates direct from indirect verif Oct 2, 2026 ↗

In operation

1,250 direct and 3,750 indirect jobs in operation, direct and indirect stated separately verif Oct 2, 2026 ↗

The place where it is built

Andalgalá, Catamarca, before the RIGI: the official snapshot of November 2023, counting the people who live there.

Registered jobs held by people who live there

5,323 jobs in November 2023, 65% of them in public administration verif Nov 2023 ↗

Miners and construction workers who live there

791 jobs: 251 in mining and 540 in construction verif Nov 2023 ↗

Miners who live there, 2018 versus 2023

from 145 to 251 jobs verif Nov 2023 ↗

Lodging businesses with employees in the department

5 in 2022 verif 2022 ↗

Mining wage versus public-sector wage

4.8 times estim Nov 2023

The works versus the place

0.4 times all registered jobs in the department and 2.5 times its miners and construction workers estim Nov 2023

The works that stay behind

The project has not reached this stage yet

The project has been filed under the RIGI and has not been approved yet. Permanent works are documented once construction starts.

What it already pays in taxes and royalties

The project has not reached this stage yet

The project has been filed under the RIGI and has not been approved yet. Royalties and production taxes begin with operation.

Who promised what

Pending

We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall it

risks and how to track them
Pending · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified this

the act, the gaps and the sources

The RIGI act, in detail

The project has not reached this stage yet

The project has been filed under the RIGI and has not been approved yet. The instrument is published in the Boletín Oficial once the Committee approves the accession.

What we could not confirm

There are 4 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01The RIGI Comité Evaluador approval announced on Oct 2, 2026+

It is announced by the national Government and by Glencore itself, but there is no resolution in the Official Gazette and the project does not appear in the official list of approved projects. An act of State requires publication: that is why the project is still counted as filed.

What would close itThe admission resolution published in the Official Gazette, with the eligible amount, the schedule and the commitment to purchase from local suppliers.
H-02When construction starts and when operation begins+

The official announcement gives works from November 2027 and operation from October 2031, but these are forecasts attributed to the company: the binding schedule is read in the recitals of the admission resolution, which has not been published in the Official Gazette.

What would close itThe RIGI admission resolution published in the Official Gazette, which is where the Ministry transcribes the declared construction time and the estimated start of operation.
H-03Which contractors Agua Rica has awarded+

None. Everything awarded and published in the province by Glencore belongs to the Bajo de la Alumbrera restart —the heavy fleet of more than USD 250 M with the brand's dealer, and three rotary drill rigs— not to the construction of Agua Rica, which has not started. Two independent investigations of this project reached the same conclusion separately, and that is what makes it a finding: when two searches that did not read each other declare the same gap, the absence is a fact and not a search failure.

What would close itThe RIGI adhesion resolution published in the Boletín Oficial, and the filing of the exploitation environmental impact report. Before that there is no work to award.
H-04The provincial environmental file of the project, which is the clock everyone is watching+

The executive summary of the expansion of Declaración de Impacto Ambiental 418 and the 2025 public-participation disposition are published on the Government of Catamarca portal, and today they could not be opened: the entire catamarca.gob.ar domain sits behind an automated anti-robot control that yields neither to a page reader nor to a browser. The gap is one of access, not of existence: we know the documents are there. ✅ UPDATED 18 Sep 2026: the Environmental Impact Report for the exploitation stage has now been filed (8 Sep 2026) and is under evaluation — what still cannot be opened is the file on the provincial portal, so the Environmental Impact Declaration still does not exist and its clock is still running.

What would close itA copy of the two PDFs through a route the gate does not block, or the provincial Boletín Oficial. That is what would let us date, with an act of its own, the advanced-exploration filing that today rests only on the dossier.
First step · free
The first read of your company

We look at what your company does and tell you whether we see a sign that it fits this market, with the evidence behind it. If we do not see one, we say so too and name the condition that would change it. One page as a dated PDF, within 48 working hours.

Not here for a company? Invest · Work (in Spanish) · Start a business (in Spanish) · Institutions
Page 1 of the example executive summaryOpen the report ↗A real analysis · a real company, open in full →
Ignacio Aredez
Analysis and curation: Ignacio Aredez
Head of Despegue
Method and track record →
  • 20+ years in technology, 15 of them in data and AI, for clients across Europe and the Americas
  • Certified in AI governance (ISO/IEC 42001)
  • Machine Learning (Google Cloud)
  • Registered expert with the European Commission
How to read the seals →
  verif primary source · prob primary source pending · unconf a source said it · estim our own calculation · thesis our reading · the date belongs to the datum, at the precision its source allows
This is not financial advice. The page is built on the act that approved the project and the source of every figure, with the gaps declared. What the company announces is published as an announcement, and what is our own reading is labeled as thesis. ← Back to Catamarca