Despegue ← Projects Proyecto RIGI
The 31 projectsPROJECT ▾
Neuquén
YPF 'LLL Oil' (shale-oil mega-development)Pluspetrol - Bajo del Choique / La InvernadaTecpetrol - Los Toldos II EstePampa Energía - Rincón de ArandaTGS - Natural gas liquids (NGL) project, Tratayén - Bahía BlancaAmpliación Mega - natural gas liquids (NGL)
San Juan
Vicuña (Josemaría + Filo del Sol) — copper, gold and silverEl Pachón - copper, silver and molybdenum (Glencore)Los Azules — copper cathodes (McEwen Copper)Gualcamayo — Deep Carbonates (DCP): gold and silver (Minas Argentinas)Leaching Phases 8 and 9 expansion — Veladero Mine (gold)
Catamarca
Agua Rica / MARA — copper, gold, silver and molybdenum (Glencore)Salar Tres Quebradas (3Q), stage 2 — lithium carbonate (LIEX/Zijin)Fénix — Phase 1B Expansion: lithium carbonate (Minera del Altiplano / Rio Tinto)Hombre Muerto Oeste (HMW) — lithium carbonate (Galan)
Río Negro
Argentina LNG (YPF, Eni and XRG)Southern Energy - floating LNG (Argentina LNG, Hilli phase)Vaca Muerta Oleoducto Sur (VMOS)San Matías Gas Pipeline (San Matías Pipeline S.A.) - evacuation of Vaca Muerta gas to the Atlantic
Salta
Pozuelos-Pastos Grandes (PPG)Rincón Project — lithium carbonate (Rio Tinto)Diablillos — gold and silver (Salta/Catamarca)Sal de Oro II — lithium carbonate (POSCO)
Buenos Aires
Fértil Pampa — urea and ammonia plant in Bahía BlancaSidersa Argentine Steel Project — long steel productsOlavarría Wind Farm (P.E. Olavarría) — wind generation (GEAR I / PCR + ArcelorMittal Acindar)
Mendoza
PSJ Cobre Mendocino (San Jorge) — copper and goldEl Quemado Solar Park and Annexes — photovoltaic generation (Luz del Campo SA / YPF Luz)
Jujuy
Cauchari-Olaroz Expansion — lithium carbonate (Exar)
La Pampa
Perito Moreno Gas Pipeline expansion (ex-GPNK) - TGS
Santa Fe
Timbúes Multipurpose Terminal — port infrastructure (Terminal Timbúes SA)
ESEN
up to date · reviewed Oct 15, 2026
Energy - Oil and Gas (shale)/Neuquén
submitted

Pluspetrol - Bajo del Choique / La Invernada

announced investment
12.400USD M
operator
Pluspetrol 90% / GyP (Gas y Petróleo del Neuquén) 10%
what it will need
2procurement fronts

Development of the asset Pluspetrol bought from ExxonMobil. Peak of 100,000 bbl/d + 12 MMm3/d, +600 wells. Includes GyP's 10% carry.

Summary
share among the 8 filed RIGI projectstotal USD 109,241 M
Pluspetrol11.4%
the other 7USD 96,841 M
what stage it is atunder construction prob Mar 2026 ↗

How to supply it

what we have for a supplier, and how to request it

What we have on this project for a supplier

How to get in
1 registration route, with its status · 2 requirements with the rule that sets each one · 5 steps in order, with their timing

Who decides the purchase, who you invoice and where a new supplier registers.

What it buys and when
3 phases, with what each one buys · 1 happening now

Which lines each phase buys and when the window opens for each one.

What it is missing
2 services it will need and has no supplier for yet

Which they are, why it will need them and who could provide them.

Who is already in
3 companies with a contract on the works · 1 with their own purchasing door

Who they are, what each one does and how to sell to them.

All of this is surveyed and verified against its source. Crossed with what you sell —which of them your products suit, how to reach it and when— it is in your company report. Request the report

Does your company fit into Pluspetrol?

We cross what you manufacture or do against the 3 phases of this project and tell you which ones you fit into and when each one buys. Two pages, with the evidence behind them.

Where my company can get in

The project

what it is, the route, the owners, the works and the contractors

Who owns it

Pluspetrol 90% / GyP (Gas y Petróleo del Neuquén) 10% prob Apr 23, 2026 ↗

The works, milestone by milestone

Oct 2, 2026rigi announcement

The government of Neuquén reports that the Comité Evaluador approved the project's admission to the RIGI: USD 12,400 million over 25 years, four processing plants, evacuation pipelines, more than 620 horizontal wells with three dedicated drilling rigs and an average of 41 wells a year, to exceed 100,000 barrels a day. The Minister of Economy publishes on the same day USD 12,240 million, 620 wells and more than 2,300 jobs across construction and operation, and the provincial release speaks of more than 4,000 people over the next year and a half.

Oct 2, 2026works plan

The trade press reports that the operator replaced the idea of a central plant with modules of about 25,000 barrels a day each, and that the next module is scheduled for April 2027.

Apr 23, 2026rigi application

Pluspetrol, which operates the area with 90 % against Gas y Petróleo del Neuquén's 10 %, announces it will file the RIGI adhesion application: USD 12 billion, four processing plants, more than 600 wells and a declared peak of 100,000 barrels a day and 12 million cubic metres of gas a day, over 25 years in two stages.

Mar 31, 2026environmental hearing

Public environmental hearing for the project at the Kacike hall in Rincón de los Sauces, at 12:30, under article 31 of provincial Ley 1875, with the applicant identified as Pluspetrol Cuenca Neuquina SRL. The observations were added to the file for technical assessment.

Mar 2026new capacity

The operator's country manager says the block's first modular plant is about to be finished: «In the next thirty days we will finish EPF 1, which will add another 25,000 barrels of treatment capacity», within a modular approach «with 25,000-barrel plants to scale alongside the drilling plan».

Feb 6, 2026public hearing called

Neuquén's Official Gazette publishes the notice calling the environmental public hearing: it «will be held on March 31, 2026 at 12:30, at Salón de Eventos Kacike, on the corner of República Argentina and Juan José Castelli in the town of Rincón de los Sauces». The file is EX-2026-00234438- -NEU-SARN#MTUR and the Register of Speakers closes 5 business days before the event.

Jan 22, 2026environmental study

The «Desarrollo de Bajo del Choique» global environmental impact study is signed, prepared by Geólogos Asociados S.A. It is the document that measures the works: 150 unconventional wells on 29 pads across 25 locations, 50 sites, two treatment plants, 215,516 metres of pipelines in 129 segments and 61,710 metres of roads.

Mar 27, 2025work completed

Works on the Bajo del Choique Nordeste oil pipeline are completed: 42 km for a maximum flow of 60,000 barrels per day, API 5L standard, with monitoring fibre optics and shut-off valves. It was built by Víctor Contreras S.A. and reaches the Auca Mahuida station. An earlier article from the same outlet, from June 2024, described it as 43 km and 12 inches, with two valve stations, and warned that in the initial phase the flow was limited to 12,000 barrels per day by the pumps and the 6-inch sections prob.

Feb 18, 2025vertical integration

Pluspetrol and Weatherford agree the transfer of the fracturing services division: «the fracturing set and the main assets tied to its operation, the associated operating bases, and the workforce» verif. With that division Pluspetrol builds its own services company, SPI, which starts working in May 2025 and that year performs all its fracturing stages for the group prob.

Nov 26, 2024change of control

Decreto 1512/2024 approves the agreement between Gas y Petróleo del Neuquén and ExxonMobil Exploration Argentina over the change of control of the area, with a payment to the Province of «ONE HUNDRED MILLION UNITED STATES DOLLARS (USD 100,000,000)» for the contractual readjustment, and exempts that agreement from stamp duty.

Dec 9, 2015provincial concession

Decreto 2444/15 grants Gas y Petróleo del Neuquén the unconventional exploitation concession over the unified La Invernada – Bajo del Choique area, covering 400.27 km², for 35 years from the decree, with an initial five-year pilot plan of USD 229 million between 2016 and 2019. It envisages a development of 556 horizontal wells for about USD 13,900 million, and sets the joint venture split at 10% for Gas y Petróleo del Neuquén and 90% for ExxonMobil.

What it leaves in Neuquén

jobs, works, taxes, promises and the outlook

The works that stay behind

The infrastructure that stays standing once the works end, with its size and its source.

Bajo del Choique Nordeste pipeline

Productive
42 km

and a capacity of 60,000 barrels per day (a June 2024 article gave it as 43 km and 12 inches)

the block and, through the Auca Mahuida station, the evacuation system of the whole basin

Works completed in March 2025. API 5L standard, design pressure of 101.24 kg/cm², monitoring fibre optics and shut-off valves; a June 2024 article spoke of two valve stations. thesis It is the only permanent work tied to the project that is already finished.

Two treatment plants, EPF#3 and EPF#4, on a single site

Productive
25,000

barrels of oil, 3.0 million m³ of wet gas and 27,500 barrels of produced water a day EACH, on a 700,000 m² site (700 × 1,000 m)

the block: they are what leaves the water fit for reinjection, the crude fit for sale and the gas to sales specification

Verbatim from the environmental study: «These plants will share the same design and a maximum processing capacity of 25,000 bopd of oil, 3.0 MMSCMD of wet gas and 27,500 bwpd of produced water each». The same document publishes the equipment list for the two plants: 118 units of 35 types, from three-phase separators and compressors to TEG columns, pumps and gas gensets. thesis It is the most detailed purchasing map this project has made public.

Pipeline network of the development

Productive
215,516

metres in 129 segments: 67,630 m of trunk and interconnection lines (27 pipelines), 36,120 m of gas and liquids evacuation (2), 21,130 m in BIN C (34), 29,730 m of injection to disposal wells (7), 26,282 m of water and fuel gas (14), 14,790 m in BIN D (15) and 19,834 m in BIN E (30)

the block for the whole concession: it is the link between well pads, plants and delivery point

The environmental study breaks the pipelines down by family and by number of segments. ⚠️ The document itself states that the pipelines are reversible: at the abandonment stage they «will be removed from the project site for reuse or final disposal».

Trunk roads and access roads to facilities

Roads
61,710

metres, with an average width of 6 metres

the area: the study itself describes the prior setting as one of «dirt roads, with very low to no maintenance» and «very low road density», and roads are the only thing the abandonment plan does not remove

Verbatim from the environmental study: «Construction of trunk and facility access roads, totalling: 61,710 m of road, with an average width of 6 m». Access to the site of the two plants adds a new 12-metre-wide stretch with a maximum longitudinal gradient of 6 % and a finish of load-bearing material at least 0.2 m thick, compacted.

Fracturing sand hub

Productive
70,183

m² (216 × 324 m), with entry and exit weighbridges, unloading yards on a concrete slab and conveyor belts

the block and the area's sand logistics: it is the facility that sets how many sand trucks come in per day

The environmental study places the hub on a site of «70,183 m2 (216 m x 324 m)» and sizes its equipment against the number of trucks a day entering the plant.

Contractors' accommodation camp (BIN D)

Social
60.000

m² (300 × 200 m)

the block's contracting companies: the site is divided into areas assigned to each of them for their own site offices

Verbatim from the environmental study: «Within the camp compound, areas will be assigned to each contractor for the installation of their site offices». It includes a barrier with access control, a multi-purpose hall, parking, office trailers, a canteen, washrooms, power generation, fuel storage, segregated waste disposal, a sewage treatment plant and a medical service. Each contractor installs its own modular effluent treatment plant. thesis It is the most concrete way in that the project publishes.

Two freshwater storage ponds

Water
no figurea 397 × 210 m site, with two ponds of 151 × 130 m set 15 m apart and 6 metres of excavation depth

the block: it is the facility that sets how much fracturing water the development can sustain

Verbatim from the environmental study: «The area proposed for the construction of the ponds is 397 m x 210 m. Each pond will be 151 m X 130 m, set 15 m apart. Total excavation depth will be 6 m». It is completed by 6 water intake wells, 7 disposal wells and 7 monitoring wells.

What it already pays in taxes and royalties

The project has not reached this stage yet

The project has been filed under the RIGI and has not been approved yet. Royalties and production taxes begin with operation.

Who promised what

Pending

We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall it

risks and how to track them
Pending · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified this

the act, the gaps and the sources

The RIGI act, in detail

The project has not reached this stage yet

The project has been filed under the RIGI and has not been approved yet. The instrument is published in the Boletín Oficial once the Committee approves the accession.

What we could not confirm

There are 5 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01The RIGI Comité Evaluador approval announced on Oct 2, 2026+

There are two official announcements on the same day, from the government of Neuquén and from the Minister of Economy, and they do not agree on the amount: USD 12,400 M versus USD 12,240 M. There is no resolution in the Official Gazette and the project does not appear in the official list of approved projects. An act of State requires publication: that is why the project is still counted as filed.

What would close itThe admission resolution published in the Official Gazette, which sets the total amount, the eligible amount, the schedule and the commitment to purchase from local suppliers.
H-02When construction starts and when operation begins+

The schedule of a RIGI project is read in the recitals of its admission resolution, and this project has no resolution published in the Official Gazette yet: it has been filed or announced, not approved. What circulates in the press are tentative company dates, with no act fixing them.

What would close itThe RIGI admission resolution published in the Official Gazette, which is where the Ministry transcribes the declared construction time and the estimated start of operation.
H-03Who is building the two EPF#3 and EPF#4 plants, the 215 km of pipelines and the 61.7 km of roads+

The work is measured down to the metre in the environmental study, but neither research pass found a published contractor. And there is a trap the document itself flags: the waste, aggregate and water providers the study lists are NOT chosen contractors — the text names them «by way of example» and clarifies that «this list is not exhaustive, since the contractor selected will depend on holding current permits and on commercial terms».

What would close itThe project sheet on the builder's own site, or the report of a presentation to a local business chamber, which is where the civil works contractors of other projects in this dataset turned up. The third modular plant was «in the tendering period» in August 2026, so that is the nearest window.
H-04The area's royalty rate+

Decreto 2444/15 has already been read: it sets the 35-year term, the surface area and the 10/90 joint venture split, but does not include the royalty rate. It only certifies that ExxonMobil, now replaced by Pluspetrol, pays 100% of the block's royalties.

What would close itThe Agreement of 4 December 2015 between the Province, Gas y Petróleo del Neuquén and ExxonMobil, annexed to the decree, which is where the rate lives.
H-05How many plants are actually running, against the four the RIGI application declares+

The figures do not line up and they carry different dates: the application declares four processing plants, the environmental study projects two, the early production unit came into service in November 2025, the first of the modular plants was to add its module within the thirty days following March 2026, according to its country manager, and a third was listed «in the tendering period» in August 2026. It is not a contradiction: they are different perimeters and different moments that no source reconciles.

What would close itThe RIGI enrolment resolution, which is where the Ministry sets out the detail of the computable facilities, or the environmental decision on the file under way.
First step · free
The first read of your company

We look at what your company does and tell you whether we see a sign that it fits this market, with the evidence behind it. If we do not see one, we say so too and name the condition that would change it. One page as a dated PDF, within 48 working hours.

Not here for a company? Invest · Work (in Spanish) · Start a business (in Spanish) · Institutions
Page 1 of the example executive summaryOpen the report ↗A real analysis · a real company, open in full →
Ignacio Aredez
Analysis and curation: Ignacio Aredez
Head of Despegue
Method and track record →
  • 20+ years in technology, 15 of them in data and AI, for clients across Europe and the Americas
  • Certified in AI governance (ISO/IEC 42001)
  • Machine Learning (Google Cloud)
  • Registered expert with the European Commission
How to read the seals →
  verif primary source · prob primary source pending · unconf a source said it · estim our own calculation · thesis our reading · the date belongs to the datum, at the precision its source allows
This is not financial advice. The page is built on the act that approved the project and the source of every figure, with the gaps declared. What the company announces is published as an announcement, and what is our own reading is labeled as thesis. ← Back to Neuquén