up to date · reviewed Aug 19, 2026
Energy - wind power generation (180 MW)/Buenos Aires
approved

Olavarría Wind Farm (P.E. Olavarría) — wind generation (GEAR I / PCR + ArcelorMittal Acindar)

total investment in the act
275,6USD M

A 180 MW wind farm near Olavarría (Buenos Aires), owned by GEAR I (PCR + ArcelorMittal Acindar). 30 latest-generation wind turbines (6 MW each); partial self-supply for Acindar's steel plants. It includes a new transformer station and ~25 km of 132 kV line. It is one of the few RIGI projects in Buenos Aires and a case of renewable energy tied to an industrial consumer (captive PPA). ⚠ The 'Res 137/2026' from the Energy Secretariat that circulated is NOT the RIGI admission.

operator
GEAR I S.A. Dedicated Branch PEO
approving act
Resolución 1254/2025
what it will need
2procurement fronts
Summary
share among the 22 approved RIGI projects we tracktotal USD 33,041 M
Olavarría Wind Farm0.8%
the other 21USD 32,765 M

The projectwhat it is, the route, the owners, the works and the contractors

Who owns it

GEAR I S.A. Dedicated Branch PEO (VPU, CUIT 30-71903605-4); parent Generación Eléctrica Argentina Renovable I S.A. (CUIT 30-71592816-3), owned by PCR (Petroquímica Comodoro Rivadavia) and ArcelorMittal Acindar verif · Aug 27, 2025

We have not worked on this yet · 2 blocks
  • The works, milestone by milestone — We have not built this project’s timeline. Dated milestones with their source close it.
  • Who already has a contract — We have not surveyed this project’s awards. A published contract with its source closes them.

How to supply itwhere to register, what they ask for and what they will buy

What it will need and has no supplier for yet

tesisOur own reading of the project, not company-reported data.

Wind civil works and turbine assembly (foundations, cranes, lifting of 30 turbines of 6 MW)

high

Lifting large wind turbines and their foundations demands heavy cranes, civil works and specialised blade/nacelle logistics.

Supplied byconstruction firms / wind lifting logistics

Evacuation electrical works (33/132 kV substation + 25 km transmission line) and farm O&M

medium

The substation and the high-voltage line are dedicated electrical works; the farm then requires turbine O&M.

Supplied byelectrical EPC / wind O&M services
We have not worked on this yet · 2 blocks
  • How to become a supplier — We have not built this project’s entry map. It is our gap, not a prohibition: it closes by opening the provincial register and the operator’s single window.
  • What it will buy, and when — We have not built this project’s phase → demand chain: its schedule still has to be crossed with the province’s catalogue of markets and trades.
Weekly newsletter · free

Get on board the takeoff

This week’s updates: proyectos RIGI, proveedores y datos verificados de Buenos Aires and new provinces as they launch. Free.

no spam we read every one
Which are you?
What are you looking for?
Tell us more
Your provinces empty = all
pick one or more

What it leaves in Buenos Airesjobs, works, taxes, promises and the outlook

We have not worked on this yet · 3 blocks
  • The works that stay behind — We have not surveyed this project’s permanent works. A published size with its source closes them.
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall itrisks and how to track them

We have not worked on this yet · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified thisthe act, the gaps and the sources

The RIGI act, in detail

Accession date

Jul 25, 2025 verif · Aug 27, 2025

The act’s articles, in detail

2 facts on the commitment
Deadline for the commitment

30 November 2027 to complete the minimum investment amount. 40% within the first 2 years. verif · Nov 30, 2027

Vehículo de Proyecto Único

Generación Eléctrica Argentina Renovable I S.A. Sucursal Dedicada PEO (GEAR I SDE), tax ID 30-71903605-4. verif · Aug 27, 2025

How to read the seals →   verif primary source · prob primary source pending · unconf not sufficiently backed · estim our own calculation · thesis our reading
Fact sheet built on primary sources, with the gaps declared. Back to the RIGI pipeline