Despegue ← Projects Proyecto RIGI
The 31 projectsPROJECT ▾
Neuquén
YPF 'LLL Oil' (shale-oil mega-development)Pluspetrol - Bajo del Choique / La InvernadaTecpetrol - Los Toldos II EstePampa Energía - Rincón de ArandaTGS - Natural gas liquids (NGL) project, Tratayén - Bahía BlancaAmpliación Mega - natural gas liquids (NGL)
San Juan
Vicuña (Josemaría + Filo del Sol) — copper, gold and silverEl Pachón - copper, silver and molybdenum (Glencore)Los Azules — copper cathodes (McEwen Copper)Gualcamayo — Deep Carbonates (DCP): gold and silver (Minas Argentinas)Leaching Phases 8 and 9 expansion — Veladero Mine (gold)
Catamarca
Agua Rica / MARA — copper, gold, silver and molybdenum (Glencore)Salar Tres Quebradas (3Q), stage 2 — lithium carbonate (LIEX/Zijin)Fénix — Phase 1B Expansion: lithium carbonate (Minera del Altiplano / Rio Tinto)Hombre Muerto Oeste (HMW) — lithium carbonate (Galan)
Río Negro
Argentina LNG (YPF, Eni and XRG)Southern Energy - floating LNG (Argentina LNG, Hilli phase)Vaca Muerta Oleoducto Sur (VMOS)San Matías Gas Pipeline (San Matías Pipeline S.A.) - evacuation of Vaca Muerta gas to the Atlantic
Salta
Pozuelos-Pastos Grandes (PPG)Rincón Project — lithium carbonate (Rio Tinto)Diablillos — gold and silver (Salta/Catamarca)Sal de Oro II — lithium carbonate (POSCO)
Buenos Aires
Fértil Pampa — urea and ammonia plant in Bahía BlancaSidersa Argentine Steel Project — long steel productsOlavarría Wind Farm (P.E. Olavarría) — wind generation (GEAR I / PCR + ArcelorMittal Acindar)
Mendoza
PSJ Cobre Mendocino (San Jorge) — copper and goldEl Quemado Solar Park and Annexes — photovoltaic generation (Luz del Campo SA / YPF Luz)
Jujuy
Cauchari-Olaroz Expansion — lithium carbonate (Exar)
La Pampa
Perito Moreno Gas Pipeline expansion (ex-GPNK) - TGS
Santa Fe
Timbúes Multipurpose Terminal — port infrastructure (Terminal Timbúes SA)
ESEN
up to date · reviewed Oct 3, 2026
Mining - Lithium (carbonate)/Jujuy
approved

Cauchari-Olaroz Expansion — lithium carbonate (Exar)

regime-eligible assets
1.167USD M
operator
Minera Exar Dedicated Branch
approving act
Resolución 825/2026
what it will need
1procurement fronts

First expansion of an operating lithium project to enter the RIGI as a standalone project (dedicated-branch structure): it validates the expansion route over existing assets without contaminating the incentives of the parent project. Employment estimated by the Mining Secretariat (outside the resolution's operative text): 1,787 jobs across construction and operation.

Summary
share among the 24 approved RIGI projectstotal USD 42,134 M
Cauchari-Olaroz Expansion2.8%
the other 23USD 40,967 M
what stage it is atpre-construction verif Jun 30, 2026 ↗

How to supply it

what we have for a supplier, and how to request it

What we have on this project for a supplier

How to get in
1 registration route, with its status · 5 requirements with the rule that sets each one · 5 steps in order, with their timing

Who decides the purchase, who you invoice and where a new supplier registers.

What it buys and when
3 phases, with what each one buys · 1 happening now

Which lines each phase buys and when the window opens for each one.

What it is missing
1 service it will need and has no supplier for yet

Which they are, why it will need them and who could provide them.

Who is already in
2 companies with a contract on the works

Who they are, what each one does and how to sell to them.

All of this is surveyed and verified against its source. Crossed with what you sell —which of them your products suit, how to reach it and when— it is in your company report. Request the report

Does your company fit into Cauchari?

We cross what you manufacture or do against the 3 phases of this project and tell you which ones you fit into and when each one buys. Two pages, with the evidence behind them.

Where my company can get in

The project

what it is, the route, the owners, the works and the contractors

Who owns it

Minera Exar Dedicated Branch — EXARSD (CUIT 30-71924298-3; Minera Exar = Ganfeng Lithium / Lithium Argentina JV) verif Jun 5, 2026 ↗

The works, milestone by milestone

Jun 30, 2026no plan closed yet

The owner reports that the updated development plan for the expansion is expected around the end of the third quarter of 2026, and that the environmental impact assessment has been filed but not approved.

Jun 5, 2026rigi approval

The Ministry of Economy approves the accession through Resolución 825/2026: an additional 45,000 t/year of lithium carbonate, with eligible assets of USD 1,166,677,726. It is the first project in Jujuy to obtain approval.

May 9, 2026rigi accession

Accession date to the RIGI for the «Ampliación Caucharí Olaroz» project, set by article 2 of the ruling.

Feb 6, 2026payment resumed

The fifth instalment of the Grupo Minero Los Boros agreement, USD 200,000, is paid after being suspended since August 2022.

Feb 28, 2024provincial floor

Jujuy issues Decreto Acuerdo 290-DEyP/2024, requiring mining producers to contract at least 70 % of their annual spend with registered local suppliers and to have 70 % of their payroll domiciled in the province.

Jun 9, 2023first production

The existing operation starts producing lithium carbonate.

Jan 1, 2022pond servicing

The five-year contract for servicing the evaporation ponds begins, with a consortium 49 % owned by Magna Construcciones.

Aug 21, 2019power permit

Jujuy's Official Gazette publishes the notice of Resolución 161-SCA/2019: Minera Exar makes available to the public the environmental impact study for the electricity supply to its plant, of 28 MW, with a 33 kV overhead medium-voltage line.

Mar 28, 2016mining option

Minera Exar signs the option agreement with Grupo Minero Los Boros S.A. transferring mining properties that make up part of Cauchari-Olaroz.

What it leaves in Jujuy

jobs, works, taxes, promises and the outlook

How many jobs it creates

In construction

1,787 jobs across construction and operation, according to the Mining Secretariat's estimate. ⚠️ a COMBINED figure for construction AND operation, and for direct plus indirect on top of that: it is not a construction jobs number unconf Jun 5, 2026

The works that stay behind

The infrastructure that stays standing once the works end, with its size and its source.

Double-circuit 33 kV overhead line, from the Cauchari solar park to the mine's substation

Power
56,283

metres of double-circuit 33 kV overhead line along Provincial Route 70 B, plus a 33/13.2 kV substation, the 13.2 kV networks to the ponds and wells, and underground runs to the plant, the camp and the emergency thermal station

The Puna of Susques. The line connects the operation to the Cauchari solar park — Argentina's largest, owned by the province — rather than to generation of its own: it is linking infrastructure between two assets that stay, and its route follows a provincial road.

Works described in the notice of the project's electrical environmental impact study, published in Jujuy's Official Gazette on August 21, 2019: 56,283 metres of double-circuit 33 kV overhead line, from the substation of the Cauchari photovoltaic park to the plant's substation, along the service strip of Provincial Route 70 B, for a 28 MW supply.

Battery-grade lithium carbonate plant and its evaporation pond field

Productive
no figureNameplate capacity of 40,000 tonnes per year of lithium carbonate, which the expansion takes to 85,000 by adding another 45,000

It is the project's own asset rather than a work for third parties, but it belongs in the inventory for what it drags along: a pond field of that size needs permanent servicing — the contract worth USD 4.8 million a quarter today — and it is the steadiest demand a brine operation leaves behind.

The existing plant has a nameplate capacity of 40,000 t/year and has been in production since 2023. The expansion approved by Resolución 825/2026 adds 45,000 t/year, taking it to 85,000.

Pending · 2 blocks
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall it

risks and how to track them
Pending · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified this

the act, the gaps and the sources

The RIGI act, in detail

Administrative file number

EX-2025-140126020- -APN-SCEYM#MEC verif Jun 5, 2026 ↗

Accession date

May 9, 2026 verif Jun 5, 2026 ↗

The act’s articles, in detail

4 facts on the commitment
Local content set by the act

20 % of the amount earmarked for suppliers that goes to LOCAL suppliers verif Jun 5, 2026 ↗

What that local content is calculated on

The entire investment amount earmarked for paying suppliers, goods and infrastructure works, during the Single Project's construction and operation stages verif Jun 5, 2026 ↗

Deadline for the commitment

1 July 2030 to complete the minimum investment amount. verif Jul 1, 2030 ↗

Vehículo de Proyecto Único

Minera Exar Sucursal Dedicada (EXARSD), tax ID 30-71924298-3, registered at calle Palma R. Carrillo N° 54, ground floor 7, Doctor Manuel Belgrano department, San Salvador de Jujuy. verif Jun 5, 2026 ↗

What we could not confirm

There are 3 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01How many people the construction employs and how many stay working in operation+

No RIGI accession ruling publishes the number: they say the company «proporcionó la estimación del empleo directo e indirecto del Proyecto con integración local» and do not transcribe it. The only figure in circulation — 1,787 jobs — adds construction to operation AND direct to indirect, and comes from the Mining Secretariat's portal, outside the ruling's text. It is on file with its defect declared and a `sin_confirmar` seal, not split.

What would close itThe employment study filed with the application, or a company release splitting the figure into construction and operation.
H-02How many suppliers are on the provincial register, which is what measures real competition+

Decreto Acuerdo 290-DEyP/2024 requires at least 70 % of the annual amount to be contracted with registered suppliers, but the register does not publish its roll: the suppliers subdomain returns only its title and the listing routes error out. The roll that is published is the one for PRODUCERS — 30 filings, 12 approved as of September 6, 2026 — that is, the miners, not the suppliers. Without that number you cannot measure the gap between what the rule demands and what registered supply can cover.

What would close itA freedom-of-information request to Jujuy's Ministry of Economic Development and Production, or for the register to publish its roll the way the producers' register does.
H-03Who will build the expansion+

There is no award for engineering, erection, wells or the direct extraction technology. The federal ruling approves a supplier plan at 20 % and a list of goods to import, with no names. And the owner itself reported that the updated development plan is expected around the end of the third quarter of 2026 and that the environmental impact assessment has been filed but not approved. The contractors on file are from the operation already running, not from the expansion.

What would close itThe updated development plan, and the province's environmental approval.
First step · free
The first read of your company

We look at what your company does and tell you whether we see a sign that it fits this market, with the evidence behind it. If we do not see one, we say so too and name the condition that would change it. One page as a dated PDF, within 48 working hours.

Not here for a company? Invest · Work (in Spanish) · Start a business (in Spanish) · Institutions
Page 1 of the example executive summaryOpen the report ↗A real analysis · a real company, open in full →
Ignacio Aredez
Analysis and curation: Ignacio Aredez
Head of Despegue
Method and track record →
  • 20+ years in technology, 15 of them in data and AI, for clients across Europe and the Americas
  • Certified in AI governance (ISO/IEC 42001)
  • Machine Learning (Google Cloud)
  • Registered expert with the European Commission
How to read the seals →
  verif primary source · prob primary source pending · unconf a source said it · estim our own calculation · thesis our reading · the date belongs to the datum, at the precision its source allows
This is not financial advice. The page is built on the act that approved the project and the source of every figure, with the gaps declared. What the company announces is published as an announcement, and what is our own reading is labeled as thesis. ← Volver a los proyectos