Despegue Proyectos Proyecto RIGI ESEN
up to date · reviewed Sep 6, 2026
Mining - Lithium (carbonate)/Jujuy
approved

Cauchari-Olaroz Expansion — lithium carbonate (Exar)

regime-eligible assets
1.167USD M

First expansion of an operating lithium project to enter the RIGI as a standalone project (dedicated-branch structure): it validates the expansion route over existing assets without contaminating the incentives of the parent project. Employment estimated by the Mining Secretariat (outside the resolution's operative text): 1,787 jobs across construction and operation.

operator
Minera Exar Dedicated Branch
approving act
Resolución 825/2026
what it will need
1procurement fronts
Summary
share among the 23 approved RIGI projectstotal USD 35,734 M
Cauchari-Olaroz Expansion3.3%
the other 22USD 34,567 M
what stage it is atpre-construction verif Jun 30, 2026

The projectwhat it is, the route, the owners, the works and the contractors

Who owns it

Minera Exar Dedicated Branch — EXARSD (CUIT 30-71924298-3; Minera Exar = Ganfeng Lithium / Lithium Argentina JV) verif Jun 5, 2026

The works, milestone by milestone

Jun 30, 2026no plan closed yet

The owner reports that the updated development plan for the expansion is expected around the end of the third quarter of 2026, and that the environmental impact assessment has been filed but not approved.

Jun 5, 2026rigi approval

The Ministry of Economy approves the accession through Resolución 825/2026: an additional 45,000 t/year of lithium carbonate, with eligible assets of USD 1,166,677,726. It is the first project in Jujuy to obtain approval.

May 9, 2026rigi accession

Accession date to the RIGI for the «Ampliación Caucharí Olaroz» project, set by article 2 of the ruling.

Feb 6, 2026payment resumed

The fifth instalment of the Grupo Minero Los Boros agreement, USD 200,000, is paid after being suspended since August 2022.

Feb 28, 2024provincial floor

Jujuy issues Decreto Acuerdo 290-DEyP/2024, requiring mining producers to contract at least 70 % of their annual spend with registered local suppliers and to have 70 % of their payroll domiciled in the province.

Jun 9, 2023first production

The existing operation starts producing lithium carbonate.

Jan 1, 2022pond servicing

The five-year contract for servicing the evaporation ponds begins, with a consortium 49 % owned by Magna Construcciones.

Aug 21, 2019power permit

Jujuy's Official Gazette publishes the environmental impact study for the electrical infrastructure: 56 km of double-circuit 33 kV line from the Cauchari solar park, at 28 MW.

Mar 28, 2016mining option

Minera Exar signs the option agreement with Grupo Minero Los Boros S.A. transferring mining properties that make up part of Cauchari-Olaroz.

Who already has a contract

Magna Construcciones S.R.L.Argentina
It holds both of the salar’s works relationships, and they are worth separating: it is the holder of the project’s construction services contract — which exists and is not being executed — and the owner of 49 % of the consortium that services the evaporation ponds, which does invoice every quarter. ⚠️ Both belong to the EXISTING OPERATION, not to the expansion that entered the RIGI

Two contracts with opposite numbers in the same quarter. Verbatim from the owner’s report: «No expenditures were incurred under the construction services contract for the Cauchari-Olaroz project with Magna Construcciones S.R.L. ("Magna") for the three months ended March 31, 2026»; and «Service agreement with a consortium owned 49% by Magna. The agreement, entered into in Q1 2022, relates to the servicing of the evaporation ponds at Cauchari-Olaroz over a five-year term. For the three months ended March 31, 2026, transactions under this agreement totaled $4.8 million (including VAT)». Both are reported as related-party transactions: Magna is controlled by the family of a Minera Exar director who is also a director of Lithium Argentina.

Exar Capital B.V.Netherlands
Buys materials and supplies on behalf of Minera Exar — it is the procurement logistics desk, not a contractor that carries out works

USD 7.9 million in purchases of materials and supplies in the first quarter of 2026, against USD 12.7 million in the same period of 2025. Verbatim: «These transactions are settled by Minera Exar upon delivery of the goods and receipt of supplier documentation».

Grupo Minero Los Boros S.A.Argentina
Original holder of part of the mining properties that make up Cauchari-Olaroz, transferred to Minera Exar under a 2016 option agreement — not a construction contractor

In February 2026 the fifth instalment of the agreement, USD 200,000, was paid after the schedule had been suspended since August 2022. Verbatim: «During the first quarter of 2026, the Company resumed discussions with Grupo Minero Los Boros regarding the agreed quarterly payment schedule, which had been suspended since August 2022».

How to supply itwhere to register, what they ask for and what they will buy

How to become a supplier

Who you invoice

Minera Exar Sucursal Dedicada (EXARSD), CUIT 30-71924298-3, with offices at Palma Carrillo 54, ground floor 7, San Salvador de Jujuy. ⚠️ IT IS A DEDICATED BRANCH AND THAT CHANGES WHO YOU INVOICE: the RIGI covers only the expansion, so purchasing for the operation already running still goes to Minera Exar S.A. rather than to the branch. A supplier needs to know which of the two is buying, because the customs and foreign-exchange treatment is not the same.

Who decides the purchase

Procurement runs through two desks: Minera Exar in Jujuy for the operation, and Exar Capital B.V., a group company domiciled in the Netherlands, which buys materials and supplies on behalf of Minera Exar and settles on delivery of the goods and of the supplier's paperwork. The expansion's process equipment is being handled by Ganfeng Lithium, a project partner, with engineering done in China: the local window is not the equipment but on-site erection and field services.

The registration routes that exist today, with their status. The one that is up and running is not always the official one.

Provincial Register of Local Suppliers to Mining Producers

up and running today

Created by article 1 of Decreto Acuerdo 290-DEyP/2024 within the Ministry of Economic Development and Production, which is its enforcement authority. ⭐ Being registered is not just another formality: article 5 requires mining producers to contract at least 70 % of their total annual spend «con PROVEEDORES LOCALES inscriptos en el Registro», so a sale made from outside the roll does not count towards the miner's compliance. Registration is free and is done at the front desk of the Secretaría de Desarrollo Industrial y Comercial, at Ascasubi 290 in San Salvador de Jujuy — with the paperwork on a USB drive, which is mandatory — or through the site's digital form.

Go to the single windowabrir

What they ask you for

Local roots

Real, legal and tax domicile in Jujuy, maintained for at least two years after registering; and, for a company, 50 % or more of the capital in the hands of Jujuy-domiciled shareholders, or a branch or representative office in the province verif Feb 28, 2024 Verbatim from article 3 of Decreto Acuerdo 290-DEyP/2024: «Constituir y mantener domicilio real, legal y fiscal en la Provincia de Jujuy. El cual deberá mantenerse vigente por al menos dos (2) años luego de realizada la inscripción. Para el caso en que el proveedor sea una persona jurídica, deberá estar inscripta en la Provincia de Jujuy y que el cincuenta por ciento (50%) o más de su composición societaria, esté en poder de uno o más socios o accionistas con domicilio real o legal en la Provincia; o que establezca sucursal u oficina de representación en la Provincia».

Local roots

At least 70 % of your own payroll with real domicile in Jujuy, and professionals registered with the provincial licensing body for at least a year verif Feb 28, 2024 Verbatim from article 3, subsection b): «Verificar que al menos el setenta por ciento (70%) de su nómina de trabajadores tengan domicilio real en la Provincia de Jujuy, garantizando su permanencia; en el caso de profesionales y técnicos especializados, deberán estar matriculados en el correspondiente organismo habilitante de la Provincia verificando una antigüedad no menor a un año; sin perjuicio de ello, podrá requerirse un sistema progresivo de contratación».

Legal

In a temporary joint venture, at least 30 % of the parties must be local suppliers verif Feb 28, 2024 Verbatim from article 3, subsection c): «En el caso de Unión Transitoria (artículos 1.463 siguientes y concordantes del Código Civil y Comercial), las partes reunidas deben estar conformadas al menos en un treinta por ciento (30%) con proveedores locales».

Financial

No enforceable debts to the provincial state, and not bankrupt or in insolvency proceedings without the judge's authorisation verif Feb 28, 2024 Verbatim from article 4: «No podrán ser considerados proveedores locales: a) Quienes registren deudas exigibles e impagas a favor del Estado Provincial; b) Los fallidos y los concursados, salvo en el caso que éstos últimos cuenten con autorización expresa del Juez del Concurso a tales efectos».

Legal

A certificate of residence issued by the police, less than two months old, and the paperwork on a USB drive if the application is filed on paper verif The Register's rules require, for individuals, «Fotocopia autenticada del Documento Nacional de Identidad del titular» and «Certificado de residencia del solicitante, expedido por la policía y con una antigüedad no menor a dos (2) meses», among other paperwork. A paper application is filed at the front desk of the Secretaría de Desarrollo Industrial y Comercial «con la documentación correspondiente en soporte digital (pen drive excluyente)».

The order you get in by

1

Register with the Provincial Register of Local Suppliers to Mining Producers: without it your sale does not count towards the miner's 70 %, so this is the first step, not the last

2

File the application at Ascasubi 290 in San Salvador de Jujuy with the paperwork on a USB drive, or fill in the digital form; you get a file number and, once approved, a registration number with its certificate no published timeframe; the process is free

3

If the company is from outside Jujuy, set up a branch or representative office in the province, which is the alternative the rule allows to holding 50 % local capital

4

If your price ends up within 10 % of an out-of-province offer, invoke the mechanism in article 5: the miner is required to formally ask you to adjust the price and to report it to the Register, not to drop your bid

5

To sell to the expansion rather than to the operation, check which of the two legal entities is buying: the RIGI's dedicated branch or Minera Exar S.A.

What it will buy, and when

thesiswhat this project buys, and when each phase buys something different

Three phases with windows of their own: the initial 5,000 t/yr module between 2026 and 2030, the wells, ponds and the 45,000 t/yr commercial plant over five more years, and operation from December 2028. Wells and evaporation ponds buy earthmoving and geomembranes; the plant buys process equipment. They are neither the same market nor the same year.

thesiswhat this project buys, and when the act's deadline pulls the purchase forward

The full investment comes in over 90 months counted from July 2026 and the deadline to certify the minimum investment is Jul 1, 2030: that date, and not the end of the expansion, is what orders when buying happens.

thesiswhat this project buys, and when the asset leaves demand that does not expire

⭐ Here the rule reads in reverse, and it is worth saying so: what this project leaves behind is less a work for third parties than a demand for permanent service. A field of evaporation ponds of this size needs continuous maintenance, and that contract is worth USD 4.8 million a quarter today. A brine operation buys service every month; a mine under construction buys works once.

Each phase buys different things at different times.

happening now1 phase

Initial 5,000 t/yr lithium carbonate module

under way
July 2026 → 2030 (declared 4-year term)

Verbatim from the act: the completion of preliminary works in the southern area of Salar Caucharí and «the construction of an initial module for the production of five thousand tonnes (5,000 t) per year of LCE to be executed within a term of four (4) years». The investment plan for the first two years is USD 37,967,590 and USD 58,787,877.

not started yet2 phases

They are not buying any of this today. Open the phase to see the detail and arrive qualified the day it goes to tender.

Wells, evaporation ponds and 45,000 t/yr commercial plantfive additional years; 100% of the investment falls within 90 months counted from July 2026 (→ end of 2033)not startedno items
Operationfrom December 2028not startedno items
Looking for work rather than to supply? What this project leaves the people of Jujuy (in Spanish)

What it will need and has no supplier for yet

tesisOur own reading of the project, not company-reported data.

EPC and assembly of carbonate plant modules (initial 5,000 tpa module + scale-up to 45,000 tpa)

high

The expansion is essentially building a new plant next to a live operation: staged industrial assembly over ~7 years.

Supplied byEPC / metalworking
Does your company fit into Cauchari?

We cross what you manufacture or do against the 3 phases of this project and tell you which ones you fit into and when each one buys. Two pages, with the evidence behind them.

Analyze my company

What it leaves in Jujuyjobs, works, taxes, promises and the outlook

How many jobs it creates

In construction

1,787 jobs across construction and operation, according to the Mining Secretariat's estimate. ⚠️ a COMBINED figure for construction AND operation, and for direct plus indirect on top of that: it is not a construction jobs number unconf Jun 5, 2026

The works that stay behind

The infrastructure that stays standing once the works end, with its size and its source.

Double-circuit 33 kV overhead line, from the Cauchari solar park to the mine's substation

Power
56,283

metres of double-circuit 33 kV overhead line along Provincial Route 70 B, plus a 33/13.2 kV substation, the 13.2 kV networks to the ponds and wells, and underground runs to the plant, the camp and the emergency thermal station

The Puna of Susques. The line connects the operation to the Cauchari solar park — Argentina's largest, owned by the province — rather than to generation of its own: it is linking infrastructure between two assets that stay, and its route follows a provincial road.

Works described in the project's electrical environmental impact study, published in Jujuy's Official Gazette on August 21, 2019, with a capacity of 28 MW.

Battery-grade lithium carbonate plant and its evaporation pond field

Productive
no figureNameplate capacity of 40,000 tonnes per year of lithium carbonate, which the expansion takes to 85,000 by adding another 45,000

It is the project's own asset rather than a work for third parties, but it belongs in the inventory for what it drags along: a pond field of that size needs permanent servicing — the contract worth USD 4.8 million a quarter today — and it is the steadiest demand a brine operation leaves behind.

The existing plant has a nameplate capacity of 40,000 t/year and has been in production since 2023. The expansion approved by Resolución 825/2026 adds 45,000 t/year, taking it to 85,000.

Pending · 2 blocks
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall itrisks and how to track them

Pending · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified thisthe act, the gaps and the sources

The RIGI act, in detail

Administrative file number

EX-2025-140126020- -APN-SCEYM#MEC verif Jun 5, 2026

Accession date

May 9, 2026 verif Jun 5, 2026

The act’s articles, in detail

4 facts on the commitment
Local content set by the act

20 % of the amount earmarked for suppliers that goes to LOCAL suppliers verif Jun 5, 2026

What that local content is calculated on

The entire investment amount earmarked for paying suppliers, goods and infrastructure works, during the Single Project's construction and operation stages verif Jun 5, 2026

Deadline for the commitment

1 July 2030 to complete the minimum investment amount. verif Jul 1, 2030

Vehículo de Proyecto Único

Minera Exar Sucursal Dedicada (EXARSD), tax ID 30-71924298-3, registered at calle Palma R. Carrillo N° 54, ground floor 7, Doctor Manuel Belgrano department, San Salvador de Jujuy. verif Jun 5, 2026

What we could not confirm

There are 4 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01How many people the construction employs and how many stay working in operation+

No RIGI accession ruling publishes the number: they say the company «proporcionó la estimación del empleo directo e indirecto del Proyecto con integración local» and do not transcribe it. The only figure in circulation — 1,787 jobs — adds construction to operation AND direct to indirect, and comes from the Mining Secretariat's portal, outside the ruling's text. It is on file with its defect declared and a `sin_confirmar` seal, not split.

What would close itThe employment study filed with the application, or a company release splitting the figure into construction and operation.
H-02How many suppliers are on the provincial register, which is what measures real competition+

Decreto Acuerdo 290-DEyP/2024 requires at least 70 % of the annual amount to be contracted with registered suppliers, but the register does not publish its roll: the suppliers subdomain returns only its title and the listing routes error out. The roll that is published is the one for PRODUCERS — 30 filings, 12 approved as of September 6, 2026 — that is, the miners, not the suppliers. Without that number you cannot measure the gap between what the rule demands and what registered supply can cover.

What would close itA freedom-of-information request to Jujuy's Ministry of Economic Development and Production, or for the register to publish its roll the way the producers' register does.
H-03Who will build the expansion+

There is no award for engineering, erection, wells or the direct extraction technology. The federal ruling approves a supplier plan at 20 % and a list of goods to import, with no names. And the owner itself reported that the updated development plan is expected around the end of the third quarter of 2026 and that the environmental impact assessment has been filed but not approved. The contractors on file are from the operation already running, not from the expansion.

What would close itThe updated development plan, and the province's environmental approval.
H-04The project's electrical infrastructure was not opened in its primary source+

The 56,283 metres of double-circuit 33 kV line from the Cauchari solar park, with its 28 MW, come from the electrical environmental impact study published in Jujuy's Official Gazette on August 21, 2019, which has not yet been read in its original publication. It is published as `probable` and with its source declared.

What would close itThe notice in Jujuy's Official Gazette of August 21, 2019.
How to read the seals →   verif primary source · prob primary source pending · unconf a source said it · estim our own calculation · thesis our reading · the date belongs to the datum, at the precision its source allows
Ignacio Aredez
Ignacio Aredez· Chief analyst
Credentials and track record →
  • 10+ years in data science for clients across Europe and the Americas
  • Certified in AI governance (ISO/IEC 42001)
  • Machine Learning (Google Cloud)
  • Registered expert with the European Commission