Despegue Catamarca Proyecto RIGI ESEN
up to date · reviewed Sep 6, 2026
Mining - Lithium (carbonate)/Catamarca
approved

Salar Tres Quebradas (3Q), stage 2 — lithium carbonate (LIEX/Zijin)

announced investment
709USD M

Tres Quebradas stage 2: plant and infrastructure for 40,000 t/year of lithium carbonate via direct extraction (DLE), per art. 1 of Resolución 1153/2026 (all stages combined target 60,000-80,000 tpa, projected). Mine life >19 years. The official announcement of July 2026 projected ~4,406 jobs across construction and operation and exports of ~USD 400 M/yr: the act records neither figure. Third Catamarca lithium project in the regime.

operator
LIEX S.A., dedicated branch
approving act
Resolución 1153/2026
what it will need
2procurement fronts
Summary
share among the 23 approved RIGI projectstotal USD 35,734 M
Salar Tres Quebradas2.0%
the other 22USD 35,025 M
what stage it is atno public evidence prob Jul 15, 2026

The projectwhat it is, the route, the owners, the works and the contractors

Who owns it

LIEX S.A., dedicated branch (subsidiary of China's Zijin Mining group) verif Jul 14, 2026

The works, milestone by milestone

Jul 29, 2026Boletín Oficial

Resolución 1153/2026 of the Ministry of Economy is published, approving the adhesion: USD 594,136,000 in computable assets, a 40,000 t/yr plant using direct extraction, a 30-Nov-2027 deadline for the minimum investment, and 60.26% of the amount earmarked for suppliers committed to local suppliers.

Jul 3, 2026RIGI adhesion

The second stage's RIGI adhesion date, fixed by article 2 of the resolution that approved it.

Jul 17, 2022power contract

LIEX S.A. signs with POWERCHINA the project's power supply system: a photovoltaic park with more than 7 MW of storage for the salt flat and Fiambalá sites.

Who already has a contract

UT Lemiro Pablo Pietroboni S.A. — ITALCA Constructora S.R.L. — BMI Constructora S.A.Chaco and Santa Fe (Lemiro Pablo Pietroboni S.A.)
earthworks and geosynthetics for the salt flat's halite concentration ponds: crust breaking, embankment walls, base layer, geotextile and geomembrane

Two consecutive contracts for LIEX S.A. in Fiambalá, Tinogasta department. The first, 200 hectares, is declared finished: 2,040,000 m² of geomembrane, 2,040,000 m² of geotextile and 2,103,000 m² of crust breaking. The second, another 200 hectares, is declared under execution with a term of 8 months including winter: 2,078,000 m² of crust breaking, 162,000 m³ of walls, 374,000 m³ of base layer and 1,788,000 m² each of geotextile and geomembrane. The contractor publishes no amount for either work.

POWERCHINA Ltd. Sucursal ArgentinaChina
EPC of the project's power supply system: photovoltaic park with storage for the salt flat and Fiambalá sites

Contract signed on 17 July 2022 with LIEX S.A., for a photovoltaic park with «almacenamiento de energía de más de 7 MW» for the salt flat and Fiambalá sites, at 4,100 masl. The contractor's sheet, consulted today, still states that the work «actualmente se encuentra en preparación para inicio de construcción».

How to supply itwhere to register, what they ask for and what they will buy

How to become a supplier

Who you invoice

Liex S.A. Sucursal Dedicada, tax ID 30-71929244-1, domiciled at San Martín 280, San Fernando del Valle de Catamarca. It is a branch dedicated to the RIGI: the first stage's operation invoices through Liex S.A. and the expansion through the branch.

Who decides the purchase

Purchasing is decided by LIEX S.A., Zijin's Argentine subsidiary, domiciled in the provincial capital. Unlike the other three projects in the batch, here the heavy construction already has contractors identified and published by themselves, so the real door for an SME is the subcontract: the ponds joint venture and the electrical EPC are the ones buying equipment hours, geomembrane welding, transport and camp services.

The registration routes that exist today, with their status. The one that is up and running is not always the official one.

Re.P.E.M. — Catamarca's registry of suppliers to mining companies

up and running today

It is the only door that reserves a quota for a Catamarca supplier, and it is not a law: it was created by Resolución S.E.M. 498/2014, whose article 4 requires mining companies to ensure that «la cantidad total de contrataciones anuales de obras, servicios, compra de bienes y/o insumos a proveedores inscriptos en el Re.P.E.M. no deberá ser inferior al setenta por ciento (70%) del total de contrataciones con proveedores». Sub-statutory rank: it can be changed by another resolution of the same secretariat.

What they ask you for

Local roots

Actual and registered domicile in Catamarca of no less than two years' standing, with the principal place of business inside the province. This is the requirement that puts a two-year clock on any SME from another province. verif Jun 23, 2014 The eight requirements of article 5 of Resolución S.E.M. 498/2014, plus the annual renewal in article 9. The cost of entry is administrative, not technical: the resolution asks for no certification and no minimum capital.

Legal

In a company, 50% of the legal entities, partners or shareholders must have their actual or registered domicile in Catamarca; and a UTE «deberá estar compuesta mínimamente en un cincuenta por ciento (50%) por proveedores locales». That is the door the rule leaves open to get in without relocating: partner with a local firm. verif Jun 23, 2014 The eight requirements of article 5 of Resolución S.E.M. 498/2014, plus the annual renewal in article 9. The cost of entry is administrative, not technical: the resolution asks for no certification and no minimum capital.

Local roots

70% of professional, technical and administrative employees must be natives or residents of Catamarca with no less than two years' standing. verif Jun 23, 2014 The eight requirements of article 5 of Resolución S.E.M. 498/2014, plus the annual renewal in article 9. The cost of entry is administrative, not technical: the resolution asks for no certification and no minimum capital.

Legal

Municipal licence, registration as a taxpayer with the provincial revenue agency, registered constitutional instruments, the sworn statement of Annex I, and a half-yearly update of the data. Annex I also requires proof of membership in the relevant chamber of suppliers: chamber membership is a requirement of the registry. verif Jun 23, 2014 The eight requirements of article 5 of Resolución S.E.M. 498/2014, plus the annual renewal in article 9. The cost of entry is administrative, not technical: the resolution asks for no certification and no minimum capital.

Legal

«Los simples intermediarios» — plain intermediaries — are expressly excluded. verif Jun 23, 2014 The eight requirements of article 5 of Resolución S.E.M. 498/2014, plus the annual renewal in article 9. The cost of entry is administrative, not technical: the resolution asks for no certification and no minimum capital.

Legal

This project's local-content commitment is 60.26% of the amount earmarked for paying suppliers, goods and works, against a 20% floor. ⚠️ It is of the amount earmarked for suppliers, not of total investment, and «local» here means Argentine: the resolution names no provincial local-content law. verif Jul 29, 2026 60.26% of the entire investment amount earmarked for the payment of suppliers, goods and infrastructure works, during the construction and operation stages.

The order you get in by

1

Establish actual and registered domicile in Catamarca, or form the UTE with a local partner that already has the two years' standing. This is the step that sets the calendar for all the others. two years of domicile standing, or immediate if you enter through a UTE with a local firm

2

Obtain the municipal licence and register as a taxpayer with the provincial revenue agency. not published

3

Join the relevant chamber of suppliers: proof of that membership goes inside the Annex I form. not published

4

File the Annex I sworn statement with the Dirección Provincial de Promoción Social Minera, together with the registered constitutional instruments and the payroll evidencing the 70% of Catamarca employees. not published

5

Keep it alive: half-yearly data updates and annual renewal before 30 March (article 9). half-yearly and annual

6

Knock on the subcontract, which is where the door is: the Pietroboni, ITALCA and BMI joint venture has 200 hectares of ponds under execution with an 8-month term, and POWERCHINA has the power system signed. the declared term of the second stage of ponds is 8 months, winter included

What it will buy, and when

thesiswhat this project buys, and when the act's deadline pulls the purchase forward

The Article 4 deadline to certify the minimum investment is Nov 30, 2027 and the works run through Apr 1, 2029: that is almost seventeen months of difference, and all the big spending is forced onto the early side. It is the dataset's clearest case of a buying window pulled forward relative to the schedule.

thesiswhat this project buys, and when each phase buys something different

Two dated phases: construction of the process plant and infrastructure for 40,000 t/yr between June 2026 and April 2029, and operation from Apr 1, 2029. Direct extraction (DLE) changes what it buys compared with an evaporation salar: fewer ponds and more plant, chemicals and water.

Each phase buys different things at different times. The links lead to the matching market or trade.

happening now1 phase
Looking for work rather than to supply? What this project leaves the people of Catamarca (in Spanish)

What it will need and has no supplier for yet

tesisOur own reading of the project, not company-reported data.

Civil works and high-altitude plant assembly (Fiambalá/Tinogasta, ~4,300 m above sea level)

high

Building the 40,000 tpa plant next to the existing operation: peak demand for local contractors of the Catamarca Puna.

Supplied byconstruction firms / metalworking

Heavy transport and Fiambalá-to-ports logistics

high

Doubling output doubles the outbound flow of carbonate and the inbound flow of inputs (lime, soda ash).

Supplied byhauliers
Does your company fit into Salar Tres Quebradas?

We cross what you manufacture or do against the 2 phases of this project and tell you which ones you fit into and when each one buys. Two pages, with the evidence behind them.

Analyze my company

What it leaves in Catamarcajobs, works, taxes, promises and the outlook

The works that stay behind

The infrastructure that stays standing once the works end, with its size and its source.

132 kV high-voltage line between Tinogasta and Fiambalá

Power
50 km

of line, upgrading of the Tinogasta transformer station and two 60 MVA transformers in Fiambalá, financed by Zijin Liex

Fiambalá and Tinogasta. The line is paid for by the miner but stays in the provincial grid: it improves household supply and enables the growth of tourism, mining and agro-industry in the area. It was a long-standing demand of the community.

«Una inversión adicional de US$20 millones por parte de Zijin Liex», with «un tendido de 50 kilómetros, cuya finalización está prevista para los próximos meses», as of 27-Jan-2026. ⚠️ There is a second figure for the same work: Panorama Minero, on 15-Sep-2025, describes it as «una línea eléctrica de US$22 millones que beneficiará a todo Fiambalá». Both are published with their date; they are neither averaged nor resolved in favour of the higher one.

Pending · 2 blocks
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall itrisks and how to track them

Pending · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified thisthe act, the gaps and the sources

The RIGI act, in detail

Administrative file number

EX-2026-14906968- -APN-SCEYM#MEC verif Jul 29, 2026

Accession date

Jul 3, 2026 verif Jul 27, 2026

The act’s articles, in detail

5 facts on the commitment
Local content set by the act

60,26 % of the amount earmarked for suppliers that goes to LOCAL suppliers verif Jul 29, 2026

What that local content is calculated on

The entire investment amount earmarked for paying suppliers, goods and infrastructure works, during that project's construction and operation stages verif Jul 29, 2026

Deadline for the commitment

30 November 2027 to complete the minimum investment amount (art. 4). verif Nov 30, 2027

Assets computable under the regime

594136000 USD verif Jul 29, 2026

Vehículo de Proyecto Único

Liex S.A. Sucursal Dedicada, tax ID 30-71929244-1, registered at San Martín 280, San Fernando del Valle de Catamarca. verif Jul 29, 2026

What we could not confirm

There are 2 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01The split between construction and operation of the 4,406 jobs attributed to the project+

The figure in circulation —4,406 direct and indirect jobs— is a single sum of both stages and both kinds of employment, calculated by the Ministry of Economy when it approved the admission. Resolución 1153/2026 carries no employment figure.

What would close itThe employment study filed by Liex, or the breakdown behind the Ministry’s count.
H-02Which stage of the project the second batch of halite ponds under execution belongs to+

The contractor publishes the work —200 hectares, 8 months, under execution— with client LIEX S.A. and a location on the salt flat, but its project sheet carries no date and does not name the stage. And there are two possible destinations: the 2nd stage that adhered to the RIGI, or the technical upgrade of the 1st stage that Zijin itself says takes it from 20,000 to 30,000 t/yr. This is the measured trap of this front: there is physical work near the project and it may not be the project's. That is why the `estado_obra` field remains at «sin evidencia pública».

What would close itThat the contractor dates its project sheet, or that Zijin or LIEX publish a progress report separating the expansion from the upgrade of the first stage. The provincial resolution approving the 3rd update of the exploitation-stage environmental impact report would also close it.
How to read the seals →   verif primary source · prob primary source pending · unconf a source said it · estim our own calculation · thesis our reading · the date belongs to the datum, at the precision its source allows
Ignacio Aredez
Ignacio Aredez· Chief analyst
Credentials and track record →
  • 10+ years in data science for clients across Europe and the Americas
  • Certified in AI governance (ISO/IEC 42001)
  • Machine Learning (Google Cloud)
  • Registered expert with the European Commission