Despegue San Juan Proyecto RIGI ESEN
up to date · reviewed Aug 30, 2026
Mining - Gold/San Juan
approved

Leaching Phases 8 and 9 expansion — Veladero Mine (gold)

total investment in the act
436USD M

Engineering, construction, operation and maintenance of new leach pads (phases 8 and 9) at Veladero Mine, to sustain gold production and exports. Official portal: projected exports of USD 3,800 M and 1,048 jobs (direct and indirect).

operator
Minera Andina del Sol S.R.L. Sucursal Dedicada 1
approving act
Resolución 413/2026
what it will need
3procurement fronts
Summary
share among the 22 approved RIGI projects we tracktotal USD 33,041 M
Leaching Phases 8 and 9 expansion1.3%
the other 21USD 32,605 M

The projectwhat it is, the route, the owners, the works and the contractors

Who owns it

Minera Andina del Sol S.R.L. Sucursal Dedicada 1 (MAS-SD1, CUIT 30-71906943-2) verif · Apr 1, 2026

We have not worked on this yet · 2 blocks
  • The works, milestone by milestone — We have not built this project’s timeline. Dated milestones with their source close it.
  • Who already has a contract — We have not surveyed this project’s awards. A published contract with its source closes them.

How to supply itwhere to register, what they ask for and what they will buy

How to become a supplier

We have not worked on this yet

We have not built this project’s entry map. It is our gap, not a prohibition: it closes by opening the provincial register and the operator’s single window.

What it will buy, and when

Each phase buys different things at different times.

happening now1 phase

Construction of Phase 8 of the valley leach system

under way
July 2024 → May 2027

Verbatim from the act: «estimating a total construction time for Phase 8 from the month of July 2024 to the month of May 2027». Investment plan from notification: USD 79,228,583 in the first year and USD 83,169,124 in the second, with a Dec 31, 2028 deadline.

not started yet2 phases

They are not buying any of this today. Open the phase to see the detail and arrive qualified the day it goes to tender.

Construction of Phase 9September 2027 → June 2028not startedno items
Operation of the new leach padsfrom the last quarter of 2026not startedno items
Looking for work rather than to supply? What this project leaves the people of San Juan (in Spanish)

What it will need and has no supplier for yet

tesisOur own reading of the project, not company-reported data.

Certified geomembrane installation for leach pads

high

What is approved is, literally, new lined surface: two further phases of valley leaching. The pad is a lining job where the critical work is not the material but the welding of the geomembrane and its testing, because a badly made seam is a solution leak. Catamarca already has this same service measured as a niche of its own for lithium ponds; San Juan, with a gold mine expanding pads, does not, and certified installation is brought in by crews from outside the province. The window is construction of the phases, not operation.

Supplied bycertified geosynthetics installers / geomembrane weld testing

Management, audit and certification of the cyanide solution circuit

medium

Valley leaching recovers the gold with cyanide solution in a closed circuit, so expanding phases 8 and 9 expands the circuit that has to be contained, monitored and audited: balance of rich and barren solutions, leak detection, barrier control and periodic external audit under the international standard the industry requires in order to sell. It is a permanent obligation and not a construction cost, and independent audit capacity in the province is scarce: whoever provides it is often the same party that designed the installation.

Supplied bycyanide management audit / containment monitoring and environmental laboratory

Geotechnical monitoring of pad stability

medium

A valley leach pad is a structure that grows in height while it is being loaded, in a seismic, high-mountain area. Its stability is not verified once at design stage: it is instrumented and measured while it operates, with piezometers, inclinometers and topographic deformation control. The province's road works and earthmoving niche measures construction; the instrumented monitoring that runs afterwards, throughout the life of the pad, has nobody quantifying it and no local supplier.

Supplied bygeotechnical instrumentation / deformation and piezometric monitoring
Write to us · free

Get on board the takeoff

Tell us what you are looking for and we will reply. This is what we work on: proyectos RIGI, proveedores y datos verificados de San Juan.

no spam we read every one
Which are you?
What are you looking for?
Tell us more
Your provinces San Juan empty = all
pick one or more

What it leaves in San Juanjobs, works, taxes, promises and the outlook

We have not worked on this yet · 3 blocks
  • The works that stay behind — We have not surveyed this project’s permanent works. A published size with its source closes them.
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall itrisks and how to track them

We have not worked on this yet · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified thisthe act, the gaps and the sources

The RIGI act, in detail

Administrative file number

EX-2025-84957022- -APN-SCEYM#MEC verif · Apr 1, 2026

Accession date

Jan 28, 2026 verif · Apr 1, 2026

The act’s articles, in detail

3 facts on the commitment
Local content set by the act

20 % of the amount earmarked for suppliers that goes to LOCAL suppliers verif · Apr 1, 2026

What that local content is calculated on

The entire investment amount earmarked for paying suppliers, goods and infrastructure works verif · Apr 1, 2026

Vehículo de Proyecto Único

Minera Andina del Sol S.R.L. Sucursal Dedicada 1 (MAS-SD1), tax ID 30-71906943-2. verif · Apr 1, 2026

What we could not confirm

There are 1 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01How many people the Phase 8 and 9 works employ+

Resolución 413/2026 does not publish employment. It is reported that the expansion creates more than 500 direct jobs per summer season between 2026 and 2028, with 90% San Juan labour, but the outlet publishing it does not allow the article to be read. The coverage that can be opened only carries the «more than 2,300 direct and indirect jobs» that Minister Caputo attributed to Veladero and Diablillos TOGETHER, which serve for neither of them separately.

What would close itA release from Minera Andina del Sol or from the San Juan government with the workforce for the expansion alone.
How to read the seals →   verif primary source · prob primary source pending · unconf not sufficiently backed · estim our own calculation · thesis our reading
Fact sheet built on primary sources, with the gaps declared. Back to San Juan