Despegue Salta Proyecto RIGI ESEN
up to date · reviewed Aug 30, 2026
Mining - Gold and silver/Salta
approved

Diablillos — gold and silver (Salta/Catamarca)

total investment in the act
764USD M

Gold and silver mining in the puna, on the Salta/Catamarca border area: feasibility development, a 3.15 Mt/yr processing plant and full infrastructure. Official portal: 2,013 jobs (direct and indirect).

operator
PACIFIC RIM MINING CORPORATION ARGENTINA S.A.
approving act
Resolución 562/2026
what it will need
3procurement fronts
Summary
share among the 22 approved RIGI projects we tracktotal USD 33,041 M
Diablillos2.3%
the other 21USD 32,277 M

The projectwhat it is, the route, the owners, the works and the contractors

Who owns it

PACIFIC RIM MINING CORPORATION ARGENTINA S.A. (CUIT 30-67305977-1) verif · May 11, 2026

We have not worked on this yet · 2 blocks
  • The works, milestone by milestone — We have not built this project’s timeline. Dated milestones with their source close it.
  • Who already has a contract — We have not surveyed this project’s awards. A published contract with its source closes them.

How to supply itwhere to register, what they ask for and what they will buy

How to become a supplier

We have not worked on this yet

We have not built this project’s entry map. It is our gap, not a prohibition: it closes by opening the provincial register and the operator’s single window.

What it will buy, and when

Each phase buys different things at different times.

happening now1 phase

Construction of the plant and the site

under way
July 2026 → July 2029

Verbatim from the act: «estimating a total construction time from the month of July 2026, and an estimated start of operation for July 2029». It includes the 3,150,000 t/yr plant, waste dumps, stockpile areas, a service centre, a truck shop, a warehouse, offices, laboratories, a construction and operation camp, a contractors’ yard, access roads, water and power. The investment plan for the first two years is USD 98,500,000 and USD 253,900,000, with a Nov 30, 2027 deadline.

not started yet1 phase

They are not buying any of this today. Open the phase to see the detail and arrive qualified the day it goes to tender.

Operationfrom July 2029not startedno items
Looking for work rather than to supply? What this project leaves the people of Salta (in Spanish)

What it will need and has no supplier for yet

tesisOur own reading of the project, not company-reported data.

Grinding and process plant maintenance

high

It is the ONLY RIGI project in Salta with a grinding plant: 9,000 t/d (3.15 Mt/year). The copper, gold and silver dossier flags it as an open gap in the province — nobody in Salta currently maintains mills of that class, and the package (relining, liner changes, alignment, vibration analysis, heavy-gauge welding) would today be imported from Chile or San Juan. It is a high-value-per-hour service with a scheduled shutdown window, and whoever gets certified during construction goes on to operate it.

Supplied byheavy mechanical maintenance / specialized welding

Fire assay of gold and silver, and grade control

high

A silver and gold deposit controls its grades by fire assay, a laboratory line distinct from the brine characterization required by Rincón and Sal de Oro: same industry, different equipment and different accreditation. It is the hard-rock leg of Salta's laboratory niche.

Supplied byassay laboratories / geochemistry

High-altitude civil works and electromechanical assembly, 2027-2029 window

medium

AbraSilver's DFS places construction from 2027, peaking in 2028-2029 and at 4,100-4,650 m above sea level. Demand is large but CONDITIONAL, which is why this hypothesis is not sealed any higher: the project has no regulatory obstacle (environmental impact statement and RIGI already approved) and its open gate is financing, with a final investment decision expected in the second quarter of 2027.

Supplied byconstruction firms / high-altitude metalworking
Write to us · free

Get on board the takeoff

Tell us what you are looking for and we will reply. This is what we work on: proyectos RIGI, proveedores y datos verificados de Salta.

no spam we read every one
Which are you?
What are you looking for?
Tell us more
Your provinces Salta empty = all
pick one or more

What it leaves in Saltajobs, works, taxes, promises and the outlook

We have not worked on this yet · 3 blocks
  • The works that stay behind — We have not surveyed this project’s permanent works. A published size with its source closes them.
  • What it already pays in taxes and royalties — We have not broken down this project’s local fiscal contribution: the primary source that sets each item still has to be opened, and an act of the State is not published on press backing.
  • Who promised what — We have not surveyed the public promises about this project. A dated, verifiable commitment with its source closes them.

What could stall itrisks and how to track them

We have not worked on this yet · 2 blocks
  • What could stall it — We have not documented this project’s risks. An identifiable vector with its source closes them.
  • How to tell whether it is advancing — We have not defined this project’s indicators: what observable fact marks its progress still has to be identified.

How we verified thisthe act, the gaps and the sources

The RIGI act, in detail

Administrative file number

EX-2025-129214596- -APN-SCEYM#MEC verif · May 11, 2026

Accession date

Feb 26, 2026 verif · May 11, 2026

The act’s articles, in detail

3 facts on the commitment
Local content set by the act

55 % of the amount earmarked for suppliers that goes to LOCAL suppliers verif · May 11, 2026

What that local content is calculated on

The entire investment amount earmarked for paying suppliers, goods and infrastructure works verif · May 11, 2026

Vehículo de Proyecto Único

Pacific Rim Mining Corporation Argentina S.A., tax ID 30-67305977-1, registered at Balcarce 376, Floor 1, city of Salta. verif · May 11, 2026

What we could not confirm

There are 1 in this project. Each says why it could not be confirmed and what it would take to close it.

H-01How many people the construction employs and how many stay working in operation+

No RIGI admission resolution publishes the figure: the seventeen that are published state that the company «provided the estimate of direct and indirect employment of the Project with local integration» and do not transcribe it. The official RIGI portal publishes a single figure that adds direct and indirect jobs together and does not separate the two stages, and mixing them is exactly the error the `empleo` field exists to prevent.

What would close itThe employment study filed with the application, or a company release splitting the figure into construction and operation.
How to read the seals →   verif primary source · prob primary source pending · unconf not sufficiently backed · estim our own calculation · thesis our reading
Fact sheet built on primary sources, with the gaps declared. Back to Salta